1 Project Value and the Assessment Baseline Free Online FlashCards

Study 1 Project Value and the Assessment Baseline with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What does project value measure?

Back

Project value is the worth of the outcomes a project is expected to create for stakeholders, compared with what would happen without it.

02
Front

Why are budget and schedule targets insufficient to prove value?

Back

Meeting cost and schedule targets does not prove that a project created value; it may still fail to deliver its intended benefits.

03
Front

Why may one financial ratio be inadequate for judging value?

Back

No single ratio captures every relevant consideration: impacts may be hard to monetize, unevenly distributed, or uncertain. Use financial measures alongside suitable nonfinancial evidence.

04
Front

What is a project assessment baseline?

Back

A baseline is the documented reference point against which a project’s expected or actual effects are assessed.

05
Front

What information should be documented for a value-assessment baseline?

Back

Record its date, key assumptions, evidence, objectives, time horizon, and measures so the comparison is transparent.

06
Front

Why separate project-caused effects from outcomes that would happen anyway?

Back

Separate effects caused by the project from outcomes that would have happened anyway; this identifies the project’s contribution.

07
Front

How should a baseline be handled when assumptions or circumstances change?

Back

Preserve the original baseline and document approved revisions. Otherwise, changes in the comparison point can look like project improvement or deterioration.

08
Front

How is project cost different from project value?

Back

Cost is the money and resources required, including relevant ongoing and opportunity costs. A cost change affects the value calculation but does not by itself prove value changed.

09
Front

What do risk and uncertainty describe, and what are they not?

Back

Risk and uncertainty concern how outcomes may differ from estimates and how likely or consequential those differences are. They are not the same as a realized loss.

10
Front

How are feasibility and project value distinct?

Back

Feasibility asks whether a project can be delivered and operated within its constraints. Attractive potential value does not ensure feasibility, and feasibility alone does not make a project worthwhile.

11
Front

What kinds of outcomes can create project value?

Back

Value can include financial returns and nonfinancial outcomes such as safety, service quality, compliance, resilience, and customer satisfaction.

12
Front

What should a business-as-usual baseline represent?

Back

The baseline should describe the credible business-as-usual outcome, including what is likely to happen without the project.