01
Choose one
1 point

A contract requires a contractor to install slate roofing by June 1. The contractor installs a different material on that date, and the failure is not excused. Which conclusion is supported?

  1. A

    No breach, because the contractor completed some of the work.

  2. B

    A breach, because the contractor failed to meet an enforceable contractual requirement when performance was due.

  3. C

    No breach, unless the owner proves the contract has ended.

  4. D

    A breach only if the owner is automatically excused from all remaining performance.

02
Choose all
1 point

Assuming each contractual duty is enforceable and the failure is not excused, select all situations that can constitute a breach.

  1. A

    Missing a contractual deadline.

  2. B

    Leaving required work incomplete.

  3. C

    Failing to make a payment required by the contract.

  4. D

    Installing a material different from the one the contract specifies.

03
True or false
1 point

Any breach of contract is necessarily serious enough to excuse the other party from continuing to perform.

  1. A

    True

  2. B

    False

04
Written response
1 point

A contractor does the work but fails to meet a specification in the contract. What is this kind of performance called?

05
Fill in the blank
1 point

An unexcused failure to perform a contractual duty when due, defective performance, or repudiation of a future duty can constitute a .

06
Open ended
1 point

An enforceable contract requires a contractor to install slate roofing by June 1. The contractor installs a different material by that date, and the failure is not excused. Explain how to assess whether a breach occurred, and distinguish that conclusion from whether the owner may stop performing.

07
Choose one
1 point

An enforceable contract requires oak cabinets by Friday. The installer provides laminate cabinets on Friday, and the failure is not excused. Which conclusion is supported?

  1. A

    There is no breach because the installer completed the installation.

  2. B

    There is no breach unless the homeowner proves the contract is material.

  3. C

    The installation can constitute a breach because it does not meet the contractual specification.

  4. D

    The homeowner is automatically excused from all remaining performance.

08
Choose all
1 point

Select all accurate statements about how a breach of contract can occur.

  1. A

    A party may breach by failing to perform a contractual duty when it is due.

  2. B

    A party may breach by performing defectively.

  3. C

    A party may breach by repudiating a future duty.

  4. D

    Any failure is a breach even if the duty is not enforceable or the failure is excused.

09
True or false
1 point

A party’s failure to perform a contractual duty can be a breach even when the contract or applicable law excuses that failure.

  1. A

    True

  2. B

    False

10
Written response
1 point

For an unexcused failure to qualify as a breach under this definition, what must the contractual duty arise from?

11
Choose one
1 point

A contractor agrees to install a specified roof material by June 1. Which situation is an example of defective performance of the contractual duty?

  1. A

    The contractor installs the specified material by the agreed deadline.

  2. B

    The contractor installs a different material from the one specified in the contract.

  3. C

    The contractor completes work that the contract does not require.

  4. D

    The contractor delays work before the performance deadline, but still completes it as agreed.

12
True or false
1 point

A minor breach ordinarily leaves the contract in force, so the other party generally must continue performing but may seek damages for the shortfall.

  1. A

    True

  2. B

    False

13
Written response
1 point

For a failure to qualify as a breach under this rule, what must the contractual duty arise from?

14
Choose one
1 point

Which statement best describes when a missed deadline can constitute a breach?

  1. A

    Any delay is a breach, even if performance is not yet due or the failure is excused.

  2. B

    A missed deadline is a breach only if the other party can immediately end the contract.

  3. C

    A party’s unexcused failure to perform a contractual duty when due can be a breach.

  4. D

    A party breaches only when its failure is serious enough to excuse the other party’s performance.

15
True or false
1 point

A failure to perform cannot be a breach unless it is serious enough to excuse the other party’s performance.

  1. A

    True

  2. B

    False

16
Written response
1 point

In a typical breach claim, what must the claimant show resulted from the other party’s failure to perform?

17
Choose one
1 point

A contractor promises to install a specified roof material by June 1 but installs a different material. Which fact most directly shows that the contractor’s performance fell short of the contractual duty?

  1. A

    The contractor installs a different material from the one the contract specifies.

  2. B

    The contractor installs the specified material by the agreed deadline.

  3. C

    The owner prefers a different material after the contractor completes the agreed work.

  4. D

    The contract does not specify a material, and the contractor installs one.

18
Choose one
1 point

For a sale of goods, which situation generally gives a buyer options under the UCC, subject to exceptions?

  1. A

    The goods are delivered in installments, regardless of whether they conform.

  2. B

    The buyer has not yet identified any contractual requirement for the goods.

  3. C

    The buyer is dissatisfied even though the goods and tender conform to the contract.

  4. D

    The goods or their tender fail to conform to the contract, subject to applicable exceptions.

19
Choose one
1 point

An enforceable contract requires a contractor to install a specified roofing material by the agreed date. The contractor installs a different material, and no contractual or legal excuse applies. Which conclusion best follows?

  1. A

    It is not a breach unless the owner can also stop performing.

  2. B

    It is a breach if the enforceable contract required that material and the failure is not excused; whether it is serious enough to excuse the owner's performance is a separate question.

  3. C

    It is not a breach because the contractor completed the installation.

  4. D

    It is a breach only if the owner proves the contractor acted in bad faith.

20
Choose one
1 point

Under an enforceable contract, a payment becomes due today. The payer does not pay, and neither the contract nor applicable law excuses the failure. Which conclusion is best supported?

  1. A

    The party may have breached by failing to perform a due contractual duty, if the failure was not excused.

  2. B

    There can be no breach because payment is not a performance under a contract.

  3. C

    It is a breach only if the missed payment also ends the contract.

  4. D

    The party has not breached unless the other party first proves bad faith.