Environmental Performance of Infrastructure Online Quiz Questions

Use this free practice quiz with 20 questions to review Environmental Performance of Infrastructure, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

Which approach best describes how to track infrastructure environmental performance?

  1. A

    Choose a small set of goal-linked indicators, then monitor predicted impacts against observed performance and take corrective action.

  2. B

    Use a single indicator for every project and assess it only after the infrastructure is decommissioned.

  3. C

    Track indicators that are not connected to project goals, without comparing predictions with observed performance.

  4. D

    Monitor observed impacts only during planning, without checking performance during construction or operation.

02
Choose all
1 point

Select all practices that support a fair environmental comparison of infrastructure alternatives.

  1. A

    Define a functional unit describing the service being compared.

  2. B

    Apply consistent boundaries and assumptions to each alternative, including relevant life-cycle stages.

  3. C

    Compare total construction impacts alone even when capacity, service life, or reliability differs.

  4. D

    Report absolute impacts as well as normalized measures, and identify data gaps and uncertainty.

  5. E

    Treat LCA results as determining which impacts are acceptable and as capturing every local ecological or social concern.

03
True or false
1 point

True or false: Assessing infrastructure environmental performance should include energy, materials, greenhouse-gas emissions, water, land, pollution, and ecological effects.

  1. A

    True

  2. B

    False

04
Written response
1 point

Name one approach to consider first when asking whether the required service can be provided without relying on a new infrastructure project.

05
Fill in the blank
1 point

A sound infrastructure assessment considers the and the .

06
Open ended
1 point

Why should an assessment of infrastructure environmental performance consider multiple impact dimensions? Name at least four dimensions and explain one way that life-cycle stage or local context affects how an impact should be assessed.

07
Choose one
1 point

Which option is an example of an environmental performance indicator that can be tied to project goals?

  1. A

    Life-cycle CO₂e per unit of service

  2. B

    The number of project meetings held, regardless of project goals or environmental impacts

  3. C

    The name of the infrastructure contractor

  4. D

    A single indicator selected for every project without regard to its goals

08
Choose all
1 point

Select all approaches supported for improving infrastructure environmental performance across its life cycle.

  1. A

    First consider demand management, better use of existing assets, or a different system design to provide the required service.

  2. B

    Compare locations and designs to avoid sensitive habitats and minimize land take.

  3. C

    Reduce material demand through efficient design, repair, reuse, and recycling.

  4. D

    Use lower-impact materials even when they do not meet the project’s performance requirements.

  5. E

    Plan for adaptation and end-of-life reuse or responsible removal.

  6. F

    Focus only on operational efficiency and ignore water, runoff, pollution, and ecological connectivity.

09
True or false
1 point

True or false: Comparing alternatives by total construction impact alone is always a fair comparison, even when they provide different capacities, service lives, or levels of reliability.

  1. A

    True

  2. B

    False

10
Written response
1 point

What acronym names the structured method used to assess potential environmental impacts across an infrastructure project’s life cycle?

11
Fill in the blank
1 point

To assess infrastructure environmental impacts comprehensively, consider the whole and whole , from planning and material extraction through construction, operation, repair, and decommissioning or reuse.

12
Choose one
1 point

When seeking to improve infrastructure environmental performance, what should be considered first?

  1. A

    Consider whether demand management, better use of existing assets, or a different system design can provide the required service.

  2. B

    Begin by selecting lower-impact materials, without first considering whether the service can be provided another way.

  3. C

    Focus first on improving operational efficiency and defer decisions about the need for the service.

  4. D

    Plan for end-of-life removal before considering demand or system design.

13
True or false
1 point

Infrastructure performance monitoring should use indicators tied to project goals and check predicted impacts against observed performance during construction and operation.

  1. A

    True

  2. B

    False

14
Written response
1 point

What abbreviation is commonly used for carbon-dioxide equivalents in life-cycle greenhouse-gas reporting?

15
Choose one
1 point

In a fair life-cycle comparison of infrastructure alternatives, what does a functional unit define?

  1. A

    A list of the materials used to construct each alternative.

  2. B

    A defined amount of the service being compared.

  3. C

    The total construction impact of the largest alternative.

  4. D

    A prediction of which environmental impacts are acceptable.

16
Written response
1 point

Predicted impacts should be checked against what during construction and operation?

17
Choose one
1 point

Which approach best reflects a whole-system, whole-life-cycle assessment of infrastructure environmental impacts?

  1. A

    Assess only operational effects within the infrastructure site.

  2. B

    Assess construction impacts and exclude maintenance and end-of-life stages.

  3. C

    Assess the whole system and life cycle, from planning and material extraction through construction, operation, repair, and decommissioning or reuse.

  4. D

    Assess only the materials and energy used during construction.

18
Choose one
1 point

Why can comparing infrastructure alternatives by total construction impact alone be misleading?

  1. A

    Construction impacts always determine which alternative has lower life-cycle impacts.

  2. B

    Alternatives may differ in capacity, service life, or reliability, so total construction impacts alone may not represent equivalent services.

  3. C

    A functional unit removes the need to state assumptions about demand or design life.

  4. D

    Life-cycle assessment alone determines which environmental impacts are acceptable.

19
Choose one
1 point

A city is planning an infrastructure project to provide a needed service. Which approach best follows the recommended order for improving environmental performance?

  1. A

    Begin with construction materials, then focus only on lowering operational energy use.

  2. B

    First consider whether demand management or existing assets can provide the service, then reduce the impacts of the chosen solution.

  3. C

    Select the location with the lowest construction cost, then compensate for any habitat loss.

  4. D

    Start by maximizing the number of performance indicators, then decide which impacts to address.

20
Choose one
1 point

Two infrastructure alternatives have different capacities and expected service lives. What is the best way to make their environmental comparison fair?

  1. A

    Compare total construction impacts, even if the projects provide different capacities or service lives.

  2. B

    Use each project's preferred assumptions so that its strongest benefits are represented.

  3. C

    Define the service being compared and apply consistent boundaries and assumptions to each alternative.

  4. D

    Compare operational impacts only, because construction impacts occur before the service is delivered.