Timedora
Free Practice Quiz Question List

Risk-Informed Audit Planning Online Quiz Questions

Use this free practice quiz with 20 questions to review Risk-Informed Audit Planning, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

What is the central purpose of developing a risk-informed audit plan?

  1. A

    To set a fixed schedule that remains unchanged throughout the audit.

  2. B

    To connect objectives to relevant risks and organize work that gathers appropriate evidence.

  3. C

    To transfer responsibility for managing controls from management to auditors.

  4. D

    To choose procedures before understanding the activity or its risks.

02
Choose all
1 point

Which actions are part of a risk-informed audit approach? Select all that apply.

  1. A

    Understand the activity and assess risks that could prevent it from meeting its objectives.

  2. B

    Keep procedures unchanged even when new evidence reveals a significant risk.

  3. C

    Select criteria and procedures that can provide relevant evidence.

  4. D

    Plan qualified staff and workable timing, then reassess as work proceeds.

03
True or false
1 point

True or false: Once audit procedures have been planned, the team should keep them unchanged even if new evidence changes the risks.

  1. A

    True

  2. B

    False

04
Written response
1 point

A sound audit plan connects the audit’s ______ to relevant risks. Enter the single term.

05
Fill in the blank
1 point

The standards or expectations used to evaluate an observed condition are called .

06
Open ended
1 point

How should an audit team develop and adapt a risk-informed plan so that its work can support conclusions about the audit objectives?

07
Choose one
1 point

During a vendor-payment audit, new evidence reveals a risk that was not anticipated in the original plan. What should the team do?

  1. A

    Continue the original procedures and address the new risk only after the audit concludes.

  2. B

    Change the audit objectives without considering the engagement’s purpose or requirements.

  3. C

    Reassess the risks and adjust the plan or procedures when warranted, documenting and communicating significant changes.

  4. D

    Transfer responsibility for the activity’s controls to the audit team.

08
Choose all
1 point

For an audit of vendor payments, which statements describe sound links among objectives, risks, procedures, evidence, or scope? Select all that apply.

  1. A

    Inspecting approvals and receiving records can provide evidence relevant to whether sampled payments were authorized and supported by receipt.

  2. B

    Analyzing payment data for duplicates can help address a risk relevant to the audit objective.

  3. C

    Assigning auditors responsibility for managing the payment controls ensures they can evaluate those controls.

  4. D

    Specifying the system, business units, and fiscal year helps define the boundaries of the audit.

09
True or false
1 point

True or false: To ensure evidence supports audit conclusions, management should transfer responsibility for managing the activity and its controls to the auditors.

  1. A

    True

  2. B

    False

10
Written response
1 point

What term describes the standards or expectations used to evaluate an observed condition? Enter the single term.

11
Fill in the blank
1 point

A sound audit plan connects objectives to relevant and helps the team gather enough appropriate to support its conclusions.

12
Choose one
1 point

During an audit, new information changes the risks and the work needed. What should the audit team do?

  1. A

    Keep the original plan unchanged to preserve consistency.

  2. B

    Revise the plan when new information changes the risks or work needed, and document and communicate significant changes.

  3. C

    Change the audit criteria whenever a procedure produces unexpected evidence.

  4. D

    Transfer responsibility for managing the activity from management to the audit team.

13
True or false
1 point

Audit planning continues as work proceeds; the team may need to adjust its plan or procedures when evidence, risks, or limitations warrant it.

  1. A

    True

  2. B

    False

14
Written response
1 point

What audit-planning term describes the boundaries of the work, including what will be examined and what is excluded?

15
Choose one
1 point

For an audit asking whether vendor payments were authorized, accurate, and supported by evidence of receipt, which set of procedures best links the work to that objective?

  1. A

    Interview staff about the purchasing policy, without examining payment records.

  2. B

    Review the audit schedule and staff assignments.

  3. C

    Test a risk-based transaction sample, inspect approvals and receiving records, and analyze payment data for duplicates.

  4. D

    Ask management to confirm that all payments complied with policy.

16
True or false
1 point

When auditors evaluate an activity and its controls, they take over management's responsibility for managing them.

  1. A

    True

  2. B

    False

17
Written response
1 point

What audit-planning term refers to the standards or expectations used to evaluate the condition observed?

18
Choose one
1 point

Which statement correctly describes how audit criteria and procedures work together?

  1. A

    Criteria set the expectations for evaluation; procedures gather evidence about those expectations.

  2. B

    Procedures set the audit's boundaries; criteria assign staff and timing.

  3. C

    Criteria identify the audit's locations and time period; procedures define what should be happening.

  4. D

    Criteria are the conclusions; procedures are the risks that could prevent objectives from being met.

19
Written response
1 point

Complete the phrase: A sound audit plan connects audit objectives to relevant _____.

20
Choose one
1 point

Which part of the audit approach assigns suitably qualified staff and determines a workable schedule?

  1. A

    Select criteria and procedures.

  2. B

    Plan resources and timing.

  3. C

    Set objectives and scope.

  4. D

    Assess risk.