What is a change request?
A documented proposal to alter an approved project requirement, deliverable, design, process, schedule, budget, or other controlled item.
Study 1 Change Request Intake and Evaluation with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.
What is a change request?
A documented proposal to alter an approved project requirement, deliverable, design, process, schedule, budget, or other controlled item.
Why record a request promptly, even if it is incomplete?
Assign a unique ID and record it promptly, even if incomplete, so the request remains visible and traceable.
What is screening for a change request?
Screening is a preliminary check of clarity, scope, duplication, information sufficiency, and routing—not a decision about whether the change is worthwhile.
What is the approved baseline?
The approved baseline is the controlled version of the relevant plans, requirements, or products used for comparison.
What makes an evaluation record decision-ready?
Summarize the request, screening outcome, affected baseline items, impact findings, alternatives, assumptions, unresolved questions, and a recommended disposition.
Who disposes of a change request?
The authorized decision-maker disposes of the request under the project’s defined authority; the requester or analyst does not decide alone.
What information should a change log link to each request ID?
Link each request ID to its requester, submission date, description, affected items, analysis owner, status, decision and rationale, and key dates.
How should intake treat a requester’s stated urgency and priority?
Treat the requester’s desired timing, urgency, priority, and expected benefit as input, not as the project’s final assessment.
What should happen when a request lacks necessary information?
Return it for clarification or mark it pending information so missing details can be resolved.
Does a requester's urgency label permit skipping required review?
A requester’s urgency label does not authorize bypassing required review.
Which two outcomes should impact analysis compare?
Assess the consequences of both making and not making the change.
What determines the depth of change impact analysis?
Match analysis depth to the change’s scale, uncertainty, and risk; a minor wording correction needs less study than a safety-critical interface change.
Learn how project governance assigns decision authority, sets boundaries, escalates issues, and records decisions.
A 14-question quiz on project governance, decision authority, escalation, and decision records.
Learn how project governance assigns decision-making authority, accountability, delivery duties, oversight, and escalation paths.
Learn how project governance assigns decision authority, accountability, delivery responsibilities, oversight, and escalation across project roles.
Learn how to identify, map, validate, and maintain a broad, evidence-based list of people and groups connected to a project.
Learn how to identify project stakeholders systematically, document their relationships, interests, and influence, validate findings, and keep the stakeholder list current.
Learn how to plan stakeholder engagement, choose appropriate participation methods, build trust, address disagreement, and adapt a project’s approach as needs and circumstances change.
Learn how project teams monitor performance, make formal decisions at stage gates, control changes, and respond to issues through corrective action and escalation.
Apply practical principles for planning, adapting, and evaluating stakeholder engagement.
Learn how to plan audience-aware project communication, choose messages and channels, invite and respond to feedback, and handle difficult stakeholder conversations.
Learn how to identify and understand project stakeholders, tailor communication to different audiences, plan and evaluate communication activities, and improve engagement by acting on feedback.
Apply core quality-planning and delivery practices to project scenarios, including acceptance criteria, assurance and control, defect response, and evidence-based improvement.