3 Change Approval and Implementation Control Free Online FlashCards

Study 3 Change Approval and Implementation Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What information should a change requester provide?

Back

The requester describes the problem or opportunity, proposed change, justification, and known urgency or constraints.

02
Front

What should be recorded when a change request is submitted?

Back

Assign a unique identifier and record the originator, description, rationale, affected items, and requested timing.

03
Front

What should a change-decision notice communicate?

Back

Communicate the request identifier, disposition, decision date and rationale, approval conditions, assigned actions and owners, expected timing, and location of the authoritative record.

04
Front

How should an approved change be controlled during implementation?

Back

Link the request to affected items and use controlled repositories and release procedures so work targets the correct versions and updates the baseline only through authorized means.

05
Front

What information makes a change log traceable?

Back

Preserve the request and requester details, analysis and comments, decision and rationale, authority and date, actions and status, affected items and versions, verification results, release information, and closure date.

06
Front

What does the change-control coordinator do?

Back

The coordinator logs and screens requests, identifies the applicable approval authority, circulates review materials, and maintains the record.

07
Front

What is the role of technical assessors and affected stakeholders?

Back

They analyze impacts in their areas of expertise and advise the decision-maker; they do not necessarily approve the change.

08
Front

Who makes the change disposition, and when is escalation needed?

Back

A designated manager, board, or authorized group decides within its assigned scope. Changes beyond that scope may need escalation.

09
Front

What distinguishes the implementer’s role from the verifier’s?

Back

The implementer makes the authorized change, while an appropriately assigned reviewer or test function checks the implementation and required record updates.

10
Front

What does screening a change request check?

Back

Check that it is understandable, complete enough to assess, within scope, and routed to the correct authority; return incomplete requests for clarification.

11
Front

What should a change impact analysis examine?

Back

Assess benefits, alternatives, risks, and effects on relevant requirements, interfaces, dependent work, cost, schedule, quality, safety, security, testing, and documentation.

12
Front

What are typical change-request dispositions?

Back

Typical dispositions are approve, defer, or reject. Approval may set conditions, responsibilities, timing, or verification requirements.