3 Escalation Paths and Issue Resolution Free Online FlashCards

Study 3 Escalation Paths and Issue Resolution with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What is escalation in project governance?

Back

A planned transfer of a risk, issue, conflict, or decision to someone with the authority or capacity to address it.

02
Front

What distinguishes a project risk from an issue?

Back

An uncertain event or condition that could affect project objectives. It may become an issue if it occurs.

03
Front

When should a project risk be escalated?

Back

Escalate when exposure exceeds agreed tolerance, crosses project boundaries, or exceeds the current owner's authority or resources.

04
Front

When should an issue be escalated, and what should be tracked?

Back

Escalate if it threatens objectives, remains unresolved past its agreed deadline, or requires authority the current owner lacks. Track its owner, actions, and age until resolution or formal acceptance.

05
Front

How should a project conflict be handled?

Back

First seek resolution between the accountable parties. Escalate if they cannot agree, a shared resource or dependency is affected, or delivery is threatened.

06
Front

When does a project decision need escalation?

Back

Escalate when a choice exceeds delegated authority, such as changing approved scope, funding, or commitments, or when delay itself threatens delivery.

07
Front

What is the work owner's role in the escalation path?

Back

The work owner or specialist identifies and assesses the matter, acts within assigned authority, and alerts the project manager when help or a decision is needed.

08
Front

How should project escalation thresholds be set?

Back

Set measurable limits against the approved plan and delegated authorities. Consider cost, schedule, scope, quality, benefits, safety, compliance, and reputation; example values are not universal standards.

09
Front

What response expectations should an escalation process define?

Back

Define how quickly matters must be acknowledged, assessed, escalated, and decided. Set timelines for the project's risk and governance context, and do not wait for a meeting if delay could increase harm or reduce options.

10
Front

What information makes an escalation actionable?

Back

Include what happened or may happen and when; impacts and dependencies; actions taken, owner, and deadline; options and recommendation; and the decision or support required, authorized person, and due date.

11
Front

What should the receiving authority do after an escalation?

Back

Acknowledge it, assign a decision owner, decide whether more analysis is needed, and communicate a decision or next step within the agreed time. Record the outcome and update relevant logs.

12
Front

What is the project manager's role in escalation?

Back

The project manager coordinates analysis and response, resolves matters within project tolerances, assigns owners, and escalates matters beyond those limits.