2 Governance Roles and Accountability Online Quiz Questions

Use this free practice quiz with 20 questions to review 2 Governance Roles and Accountability, test your knowledge, and prepare for your next test or exam.

20 questions
01
True or false
1 point

True or false: A project sponsor is responsible for managing the project team’s daily work.

  1. A

    True

  2. B

    False

02
Fill in the blank
1 point

Complete the first step of the governance escalation path: The raises an issue or decision with the project manager.

03
Written response
1 point

In the RACI convention described here, what role identifies the owner who is answerable for a result?

04
Choose one
1 point

Which responsibility best fits the project team’s usual role?

  1. A

    Approve changes to the project mandate as a routine team responsibility

  2. B

    Perform project work and raise risks, dependencies, and problems promptly

  3. C

    Take over the project manager’s operational decisions

  4. D

    Accept every project output on behalf of the organization

05
True or false
1 point

True or false: The project manager is automatically accountable for the business benefits the organization expects after the project.

  1. A

    True

  2. B

    False

06
Fill in the blank
1 point

After an authorized governance decision is made, the decision and its rationale should be .

07
Choose one
1 point

A project manager is considering an operational decision. Which condition means the manager may generally decide without escalation?

  1. A

    Any decision affecting project scope, regardless of its impact

  2. B

    Only decisions explicitly approved by the steering committee

  3. C

    Operational decisions within agreed scope, budget, schedule, and other tolerances

  4. D

    All decisions about business benefits after project completion

08
Written response
1 point

Name one type of document that should state specific governance role titles and authority arrangements.

09
Choose all
1 point

Which activities may other stakeholders perform when assigned? Select all that apply.

  1. A

    Advise on the project

  2. B

    Become accountable for overall project success solely by participating

  3. C

    Review project work or outputs

  4. D

    Provide resources or adopt the resulting change

10
Choose one
1 point

A project faces a cross-functional conflict requiring a governance decision. Which role is designed to provide oversight and make such a decision when assigned that authority?

  1. A

    The project manager, who coordinates daily delivery

  2. B

    The steering committee (or project board), which provides oversight and makes decisions assigned to it

  3. C

    The project team, which performs all specialist project work

  4. D

    Other stakeholders, who automatically approve every deliverable

11
Choose all
1 point

When documenting decision rights, which details should be recorded? Select all that apply.

  1. A

    Decision limits

  2. B

    The project manager’s preferred outcome in every case

  3. C

    Required evidence

  4. D

    The decision forum and how quickly the decision is needed

12
Open ended
1 point

A proposed change would increase project funding beyond the project manager’s authority. Describe the appropriate decision and escalation process, including what should happen after the decision is made.

13
Choose one
1 point

Users have tested a proposed system and reported defects. Who should be identified as accountable for accepting the result on the organization’s behalf?

  1. A

    The users who tested the system, because participation makes them accountable

  2. B

    The sponsor or designated business authority formally assigned accountability for acceptance, with the exact approval authority recorded

  3. C

    The project team collectively, without any assigned accountable owner

  4. D

    The project manager in every organization, regardless of delegated authority

14
Written response
1 point

A group is assigned project tasks and contributes specialist knowledge to produce the project's outputs. Which governance role does this group fill? Enter the role title.

15
True or false
1 point

A user tests a proposed system and reports defects. Because the user contributed to testing, the user is automatically accountable for accepting the result on the organization's behalf.

  1. A

    True

  2. B

    False

16
Written response
1 point

In the RACI convention described here, which term identifies the person or people who carry out the work? Enter the RACI term.

17
Choose one
1 point

A project needs continued organizational support and resources, but its routine work is already being coordinated. Which action best fits the sponsor's role?

  1. A

    The sponsor secures organizational support and resources while maintaining the case for investment.

  2. B

    The sponsor coordinates the team's routine tasks and manages daily project work.

  3. C

    The sponsor performs the specialist work needed to produce project outputs.

  4. D

    The sponsor automatically accepts every deliverable without a documented authority.

18
Choose one
1 point

A team proposes a small technical adjustment that stays within the project's approved scope, budget, schedule, and other tolerances. What should the project manager do?

  1. A

    Escalate every technical adjustment to the steering committee, regardless of its effect.

  2. B

    Authorize the adjustment if it remains within the approved tolerances and delegated authority.

  3. C

    Ask the project team to approve a change to the project's mandate.

  4. D

    Defer the adjustment until the sponsor takes over daily project management.

19
Choose one
1 point

Two affected business areas disagree about a project decision, and the governance plan assigns cross-functional conflict resolution to the steering committee. What is the committee's appropriate role?

  1. A

    Take over the project manager's daily coordination of tasks.

  2. B

    Perform all specialist project work on behalf of the team.

  3. C

    Resolve the conflict if that decision is within the committee's assigned authority.

  4. D

    Approve the conflict resolution automatically, even if the committee has no such authority.

20
Choose one
1 point

A team member identifies an issue that may need a decision. Under the stated escalation path, who should receive it first?

  1. A

    The team raises it with the project manager.

  2. B

    The team refers it directly to a higher organizational authority.

  3. C

    The team asks the steering committee to manage the project manager's daily work.

  4. D

    The team records it as resolved before identifying who has authority.