Identifying Permits and Authorizations
A practical guide to identifying the approvals a proposed activity may need, finding the right authorities, and tracking permit requirements.
Find and Track the Required Approvals
Find requirements by matching the activity and location
A is official approval to carry out an activity under specified requirements. Those requirements depend on what you propose to do, where you will do it, and which authorities have jurisdiction. A single project may need several separate approvals—for example, building, zoning, and environmental approvals.
Begin by describing the project and its location. Include details that may affect which rules apply, such as scale, operating hours, construction methods, materials handled, emissions or discharges, and effects on public land or protected resources. Then check relevant requirements at federal, state or tribal, and county or municipal levels. Federal rules may concern activities such as aviation; state or tribal requirements may cover professions or construction; local approvals commonly address zoning, building, fire safety, health, or business operations.
Use official agency and local-government information, searching by both the activity and the site. Because requirements can differ between nearby jurisdictions, do not assume that guidance for one location applies to another. Ask which approvals are required, who issues each one, and whether they must be obtained in a particular order. Keep a written record of the guidance and rules you rely on. For federal environmental programs, confirm the correct authority: administration may be direct through EPA or delegated to an authorized state, territory, or tribal government.
| Approval | Authority | Scope and status | Dates and renewal |
|---|---|---|---|
| Building permit | City building department | Proposed construction; not submitted | Effective/expiration dates: —; renewal lead time: confirm with agency |
Track approvals—and verify they are effective
A permit register helps you manage approvals separately. For each one, record the issuing authority, the activity or scope that triggers it, application status, effective and expiration dates, and how far ahead to begin renewal. This makes gaps and upcoming deadlines easier to spot.
An application alone does not usually authorize work, so confirm that each required approval has actually been issued and is effective before starting the activity. The register tracks progress; it does not replace confirmation from the relevant authority.
: A government agency or local authority with power over an activity or location.