4 Choosing an Approach for a Project Free Online FlashCards

Study 4 Choosing an Approach for a Project with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What guides the choice of a project-management approach?

Back

No single approach suits every project; choose one that fits the work, constraints, and people, and revisit it when conditions change.

02
Front

What characterizes a predictive approach?

Back

Predictive approaches define and plan work early, favoring stable, well-understood work.

03
Front

What characterizes an adaptive approach?

Back

Adaptive approaches use short cycles, feedback, and adjustment to respond to learning and change.

04
Front

What is a hybrid project approach?

Back

A hybrid approach combines practices to suit different parts or needs of the same project.

05
Front

What should a team do when project uncertainty is extreme?

Back

When uncertainty is extreme, first reduce it with a prototype or feasibility test instead of assuming a framework will solve it.

06
Front

How should requirement stability influence the approach?

Back

Requirements that can be specified and approved early suit a predictive baseline; requirements likely to evolve suit adaptive prioritization and incremental delivery.

07
Front

How should stakeholder access shape adaptive project planning?

Back

Adaptive work depends on timely stakeholder access. If feedback is infrequent or approvals are formal, plan explicit review and decision points.

08
Front

When should a project agree on measures of success?

Back

Agree on measures of success before delivery begins so the project has clear criteria for evaluating results.

09
Front

Do regulatory constraints automatically rule out adaptive work?

Back

No. Teams can build compliance checks and approvals into each iteration while maintaining traceability and release controls.

10
Front

How can dependencies affect a project's delivery approach?

Back

Many tightly coupled dependencies can require integrated planning, coordination, and milestones; independent work may proceed iteratively while shared interfaces are coordinated.

11
Front

What should be assessed to determine team readiness?

Back

Assess skills, availability, decision-making authority, tools, and access to users or specialists. Provide support or training when readiness is limited.

12
Front

When is a predictive approach a strong fit?

Back

Favor predictive planning when scope and solution are well understood, change is limited or costly, and sequencing, formal approvals, or fixed commitments dominate.