1 Project Delivery Approaches and Decision Criteria Online Quiz Questions

Use this free practice quiz with 20 questions to review 1 Project Delivery Approaches and Decision Criteria, test your knowledge, and prepare for your next test or exam.

20 questions
01
True or false
1 point

True or false: A regulated project cannot use adaptive development because regulation always requires a fully predictive approach.

  1. A

    True

  2. B

    False

02
True or false
1 point

True or false: If a project has a fixed budget, adaptive delivery guarantees that the team can deliver the originally planned scope without added risk.

  1. A

    True

  2. B

    False

03
Fill in the blank
1 point

A project has well-understood requirements, a known solution, and dependencies that can be planned. A approach is often a good fit.

04
Fill in the blank
1 point

Agile approaches generally combine —learning and improving through repeated cycles—with , which adds usable portions of the result.

05
Written response
1 point

Which project delivery category is broader than agile?

06
Written response
1 point

A project uses predictive approval gates and release planning while developing suitable features iteratively. What kind of delivery approach is this?

07
Choose one
1 point

An office renovation has a largely defined design, scope, permits, procurement plan, and construction sequence, with inspections and contractor handoffs. Which approach best fits the main delivery plan?

  1. A

    Adaptive, because any uncertainty about occupant preferences calls for repeated replanning of the whole project.

  2. B

    Predictive, because the main scope and delivery sequence are largely defined.

  3. C

    Agile, because construction work is usually divided into frequent usable software-like increments.

  4. D

    Hybrid, because every project with stakeholder input must combine two approaches.

08
Choose all
1 point

Select all conditions that support using agile practices for a project.

  1. A

    Users can review working versions regularly.

  2. B

    Users and decision-makers are rarely available for feedback or decisions.

  3. C

    The work can be divided into useful increments.

  4. D

    Early user feedback and delivery of valuable functionality are important.

09
Choose all
1 point

A regulated digital service has fixed security controls and audit obligations, but some user-facing functionality is still being discovered. Select all statements that correctly describe how the team can handle this situation.

  1. A

    Required approval gates and audit evidence can be retained while suitable features are developed iteratively.

  2. B

    A regulated project must use predictive development for every component.

  3. C

    Mandatory traceability, testing, or documentation can require defined controls and evidence.

  4. D

    Iterative work can disregard required security controls if it produces user feedback sooner.

10
Open ended
1 point

A company is building new customer-facing software. User needs and the most useful features are uncertain, but users can review working versions regularly. Recommend a delivery approach and explain how the team should use feedback during delivery. Include one limitation of your recommendation.

11
Choose one
1 point

A team is choosing how to describe an approach that works adaptively, emphasizes collaboration, and aims to deliver usable functionality frequently. Which description is most accurate?

  1. A

    Agile is a separate name for all adaptive work, whether or not it uses increments.

  2. B

    Agile is a way of working within the adaptive family that emphasizes collaboration and frequent usable increments.

  3. C

    Agile is a predictive approach that fixes scope and sequence up front.

  4. D

    Agile is a hybrid approach that always divides work equally between predictive and adaptive methods.

12
Choose one
1 point

A digital service has a fixed release date, security controls, and audit evidence requirements, while some user-facing functionality is still being discovered. Which approach best accommodates both sets of conditions?

  1. A

    Use only predictive development, because fixed release and security obligations make iterative work unsuitable.

  2. B

    Use only agile practices, because iterative feature discovery removes the need for approval gates and audit evidence.

  3. C

    Use a hybrid approach, retaining required governance and controls while developing suitable features iteratively.

  4. D

    Use adaptive development without planned release coordination, because user-facing functionality is uncertain.

13
Choose one
1 point

A product team faces uncertain requirements, but users and decision-makers are rarely available to review work or make timely decisions. Which response best fits the decision criteria?

  1. A

    Strengthen upfront definition, arrange delegated decision authority, or consider a hybrid approach.

  2. B

    Assume an agile approach will work unchanged because feedback availability does not affect it.

  3. C

    Avoid defining requirements and plans until users become regularly available.

  4. D

    Use adaptive delivery and treat missed stakeholder reviews as confirmation that the backlog is stable.

14
True or false
1 point

True or false: Planning is part of every project delivery approach, although the amount of upfront planning and the frequency of plan revisions can vary.

  1. A

    True

  2. B

    False

15
Choose one
1 point

Which statement best describes the relationship between adaptive and agile approaches?

  1. A

    Agile is the broader category, and adaptive is one of its specific methods.

  2. B

    Adaptive is the broader category, and agile is a way of working within it.

  3. C

    Adaptive and agile are unrelated approaches that cannot be combined.

  4. D

    Agile is another name for predictive delivery.

16
Choose one
1 point

A project has well-understood requirements, a known solution, and dependencies that can be scheduled in advance. Which approach is the best initial fit?

  1. A

    Use an adaptive approach because stable requirements make feedback unnecessary.

  2. B

    Use an agile approach because construction must always be divided into increments.

  3. C

    Use a predictive approach because scope and dependencies are well understood.

  4. D

    Use a hybrid approach because a fixed budget rules out upfront planning.

17
Choose one
1 point

A team expects uncertain user needs, but users and decision-makers will rarely be available during delivery. What is the most appropriate response when selecting an approach?

  1. A

    Plan for the limited feedback by strengthening upfront definition or delegating decision authority.

  2. B

    Select agile because it does not depend on stakeholder feedback.

  3. C

    Use adaptive delivery and postpone all decisions until stakeholders become available.

  4. D

    Avoid any planning because the requirements may change.

18
Written response
1 point

What project-delivery term describes adding usable portions of a result over time?

19
Choose one
1 point

A digital service has fixed security controls, audit evidence, and a release date, while some user-facing features are still being discovered. Which approach best fits these conditions?

  1. A

    Use only predictive delivery because security controls prevent iterative work.

  2. B

    Use only agile delivery because user-facing features are uncertain.

  3. C

    Use adaptive delivery without fixed release planning or approval points.

  4. D

    Combine predictive governance and release planning with iterative development of suitable features.

20
Written response
1 point

What term describes formal review points that a team may retain as part of required governance while developing some work iteratively?