4 Choosing an Approach for a Project Online Quiz Questions

Use this free practice quiz with 20 questions to review 4 Choosing an Approach for a Project, test your knowledge, and prepare for your next test or exam.

20 questions
01
True or false
1 point

True or false: One project-management approach is best for every project, regardless of its work, constraints, or people.

  1. A

    True

  2. B

    False

02
True or false
1 point

True or false: If a project has regulatory obligations, an adaptive approach is automatically unsuitable.

  1. A

    True

  2. B

    False

03
Choose one
1 point

A project has a well-understood solution, stable scope, and costly changes. Which approach is the best starting point?

  1. A

    Use predictive planning because the scope and solution are understood and changes are costly.

  2. B

    Use adaptive delivery because all work should be tested in short cycles.

  3. C

    Use adaptive delivery because fixed commitments favor frequent reprioritization.

  4. D

    Choose an approach based only on which method the team has used before.

04
Fill in the blank
1 point

When requirements are likely to evolve, an adaptive approach uses and incremental delivery.

05
Written response
1 point

Before delivery begins, what should the team agree on to evaluate whether the result succeeds? Enter the concise noun phrase.

06
Choose one
1 point

A team does not yet know whether its proposed solution is feasible. What is the best first step before settling on an approach?

  1. A

    Select a project-management framework immediately and assume it will resolve the uncertainty.

  2. B

    Run a prototype or feasibility test to reduce uncertainty before settling on an approach.

  3. C

    Commit to a detailed predictive plan even though the solution is unknown.

  4. D

    Avoid testing until the entire project has been planned.

07
Fill in the blank
1 point

To retain necessary controls during adaptive work, a team can build compliance checks and approvals into each .

08
Choose one
1 point

A project has many tightly coupled dependencies across teams and suppliers. What planning response best fits this situation?

  1. A

    Ignore the dependencies and allow each team to set unrelated delivery dates.

  2. B

    Use only short-cycle delivery because dependencies make coordination unnecessary.

  3. C

    Plan integration and coordination across the dependent work, using milestones where needed.

  4. D

    Remove all external suppliers from the project before planning.

09
Written response
1 point

Stakeholder feedback will be infrequent, and some decisions require formal approval. What should the plan explicitly include? Enter the concise planning elements.

10
Choose all
1 point

Select all the factors that directly help assess whether a team is ready to work in a proposed way.

  1. A

    Whether team members have the skills and availability the work requires

  2. B

    Whether the team prefers a familiar method, regardless of project needs

  3. C

    Whether the team has authority to make day-to-day decisions

  4. D

    Whether the team has suitable tools

  5. E

    Whether the team can access users or relevant specialists

11
Choose one
1 point

A customer portal project has defined infrastructure and privacy approvals, but its user-facing features are unclear. Which approach best fits the different needs of these workstreams?

  1. A

    Use adaptive delivery for every part, including the defined approvals, without planning review gates.

  2. B

    Use predictive planning for every part, even though user-facing features are not yet clear.

  3. C

    Use a hybrid approach: plan infrastructure and approval gates predictively, and develop user-facing features in short increments with feedback.

  4. D

    Delay all infrastructure and privacy planning until user-facing features are complete.

12
Choose all
1 point

Select all the conditions that support choosing an adaptive approach as a starting point.

  1. A

    The solution is uncertain, and the team can learn through frequent feedback.

  2. B

    The scope is stable, and changes are costly.

  3. C

    Stakeholders can give frequent feedback on useful increments.

  4. D

    Formal approvals and fixed commitments dominate, while feedback is unavailable.

  5. E

    Useful increments can be delivered and evaluated.

13
Choose one
1 point

A team has selected an approach. When should it reassess whether that approach still fits?

  1. A

    Reassess only after the project has been delivered.

  2. B

    Reassess at major milestones or when relevant project conditions change.

  3. C

    Reassess only if an individual team member prefers a different framework.

  4. D

    Reassess after every routine task, regardless of project conditions.

14
Open ended
1 point

A project sponsor asks for a repeatable way to choose and revisit a project-management approach rather than simply naming a preferred method. Outline a concise process that uses at least four assessment dimensions, explains how evidence guides the choice, and states when the choice should be reviewed.

15
True or false
1 point

True or false: Predictive, adaptive, and hybrid approaches all require planning, but differ in how much planning is done up front and how often it is revised.

  1. A

    True

  2. B

    False

16
Choose one
1 point

A project has a well-understood scope and solution, costly changes, and several formal approval gates. Which approach is the best starting point?

  1. A

    Adaptive, because short cycles are preferable even when the work is stable and changes are costly.

  2. B

    Predictive, because scope and solution are understood and formal approvals and fixed commitments dominate.

  3. C

    Hybrid, because every project with formal approvals must combine predictive and adaptive practices.

  4. D

    Adaptive, because a stable scope requires frequent reprioritization.

17
Choose one
1 point

A team is developing a product whose requirements are still uncertain. Users are available to give frequent feedback, and the team can deliver useful increments. Which approach best fits these conditions?

  1. A

    Adaptive, because the team can deliver useful increments and adjust them using frequent feedback.

  2. B

    Predictive, because uncertainty makes it especially important to lock down all requirements at the outset.

  3. C

    Predictive, because frequent feedback is incompatible with planned work.

  4. D

    Hybrid, because any uncertain requirement means some parts of the project must be regulated.

18
Choose one
1 point

A project's stakeholders can provide feedback only occasionally, and key decisions require formal approval. What should the team build into its approach?

  1. A

    Skip reviews until the project is complete so stakeholders do not interrupt delivery.

  2. B

    Use adaptive work without scheduled decision points, since formal approvals are unnecessary.

  3. C

    Plan explicit review and decision points around stakeholder feedback and formal approvals.

  4. D

    Assume stakeholders will become available more often once delivery begins.

19
Written response
1 point

When uncertainty is extreme, name one example of a step a team can take to reduce it before assuming a project-management framework alone will solve the problem.

20
Written response
1 point

When documenting a project's chosen approach, what term names the compromises to record alongside key assumptions and review cadence?