Construction Project Scheduling Free Online Flashcards

Study Construction Project Scheduling with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What does a finish-to-start (FS) dependency require?

Back

In a finish-to-start (FS) relationship, the successor cannot start until the predecessor finishes.

02
Front

What is the schedule baseline, and when should it be revised?

Back

The baseline is the approved reference plan for comparing actual progress with planned progress. Revise it only through the project’s change-control process.

03
Front

What does CPM reveal about the longest logic-connected path?

Back

CPM identifies the longest logic-connected path. Activities on that path have no total float in the calculated plan, so a delay can delay project completion unless the plan changes.

04
Front

What makes a schedule activity complete and trackable?

Back

Define activities with clear start and finish conditions so they can be assigned, estimated, and tracked. Together, they should cover planned work such as inspections, approvals, testing, and handoffs.

05
Front

What defines a useful project milestone?

Back

A milestone is a significant zero-duration event. Link it to the activities that produce it and define objective criteria for completion.

06
Front

What does a work breakdown structure (WBS) organize?

Back

The WBS organizes project deliverables into smaller components: it describes what the project will produce, not activity sequence or dates.

07
Front

At 40 m² of formwork per workday, how long for 120 m² if the crew and work area are ready?

Back

The estimate is three workdays, assuming the crew is available and the work area is ready. Constraints such as access or shared equipment may require adjustment.

08
Front

What can resource loading reveal about a schedule?

Back

Resource loading helps reveal whether the plan is feasible and whether activities compete for the same crew or equipment at the same time.

09
Front

How can schedule activities remain traceable to project scope?

Back

Use the WBS or activity codes to maintain traceability between scheduled activities and project scope.

10
Front

What should be updated and reviewed during construction schedule monitoring?

Back

Update actual starts and finishes and forecasts of remaining duration; investigate variances and emerging impacts against the approved reference plan.

11
Front

When can long-lead procurement overlap with foundation work?

Back

Long-lead procurement may proceed in parallel with foundation work when the design information and approvals needed for procurement are available.

12
Front

How does rolling-wave planning handle work that is not yet fully defined?

Back

Rolling-wave planning develops near-term work in detail and refines future work as more information becomes available.