Which dependency type describes a follow-on task that must wait until its predecessor is complete?
Construction Sequencing and Dependencies Online Quiz Questions
Use this free practice quiz with 20 questions to review Construction Sequencing and Dependencies, test your knowledge, and prepare for your next test or exam.
Select all statements that correctly describe construction dependencies or concurrent work.
- A
Concurrent work may be planned when crews have sufficient separation, access, and hazard controls.
- B
Tasks competing for a limited hoist have a resource dependency.
- C
In a start-to-start dependency, a follow-on task can begin after its predecessor starts.
- D
In a finish-to-start dependency, two tasks must reach completion together.
True or false: In a finish-to-start dependency, the follow-on task waits until its predecessor is complete.
- A
True
- B
False
What dependency type describes a follow-on task that waits until its predecessor is complete?
In a finish-to-start dependency, the follow-on task waits until its predecessor is . A dependency can occur when tasks compete for a limited resource or work area.
Describe how a team should develop a construction sequence that accounts for activity prerequisites, resource or space dependencies, and possible concurrent work.
Before scheduling a ceiling close-in, which condition best indicates that the work is ready to proceed?
- A
Proceed when the scheduled start date is approaching, even if overhead work or inspections are incomplete.
- B
Confirm overhead rough-in is complete, required tests and inspections have passed, deficiencies are resolved, and the area is ready for the next trade.
- C
Close the ceiling first and inspect the concealed work only if a problem is later reported.
- D
Proceed once materials are available, regardless of whether the preceding work is complete.
Select all items that can be constraints preventing an activity from being ready to proceed.
- A
Incomplete drawings or decisions.
- B
Unavailable materials.
- C
Blocked access.
- D
An approaching scheduled start date, by itself.
- E
Unresolved inspections.
True or false: An activity should be treated as ready merely because its scheduled start date is approaching, even if constraints remain unresolved.
- A
True
- B
False
What planning practice examines upcoming work in greater detail and removes constraints before work is promised for a particular week?
Construction activities should be sequenced according to their .
Which dependency type means a follow-on task waits until its predecessor is complete?
- A
Finish-to-start
- B
Start-to-start
- C
Finish-to-finish
- D
Resource or space dependency
True or false: A start-to-start dependency means the follow-on task must wait until its predecessor is complete.
- A
True
- B
False
What dependency type requires a follow-on task to wait until its predecessor is complete?
Which plan is an example of feasible concurrent construction work?
- A
Mechanical rough-in proceeds on one floor while framing continues on another, with separation, access, material movement, falling-object risks, and shared hoist capacity addressed.
- B
Mechanical rough-in and framing proceed in the same area at the same time, without checking access or hazards.
- C
All work is delayed until every activity in the entire project is complete.
- D
A follow-on task begins even though its required predecessor work is unfinished.
Which dependency type requires two tasks to reach completion together?
Two activities need the same hoist during an overlapping period. What type of dependency does this illustrate?
- A
Resource or space dependency
- B
Finish-to-start dependency
- C
Start-to-start dependency
- D
Finish-to-finish dependency
Which statement describes a resource or space dependency?
- A
Activities compete for a limited resource or work area, such as a hoist or access route.
- B
A follow-on task waits for its predecessor to finish.
- C
A follow-on task begins after its predecessor starts.
- D
Two tasks must reach completion together.
Waterproofing is scheduled to begin only after the concrete surface is ready. What type of dependency does this describe?
- A
The two tasks must finish together.
- B
The follow-on task waits until its predecessor is complete.
- C
The follow-on task begins as soon as its predecessor starts.
- D
The tasks compete for a shared resource or work area.
Two crews are scheduled to use the same hoist at the same time. Which dependency should the team address?
- A
A follow-on task must wait for a predecessor to finish.
- B
One task can start after another task begins.
- C
Two crews need the same hoist at the same time.
- D
Two tasks must reach completion together.
Related study packs and tools
- Study guide
1 Electrical Quantities and Ohm’s Law
Learn how charge, current, voltage, resistance, power, and energy are related in electric circuits, including how to apply Ohm’s law and interpret worked calculations.
- Flashcards
01 Foundations of Materials Science
Review how processing, structure, properties, and performance connect, and how engineering materials are classified and selected.
- Quiz
1 Vectors for Engineering Mechanics
A medium-difficulty quiz on representing vectors, calculating their components and magnitudes, and applying vector operations in engineering mechanics.
- Quiz
02 Atomic Bonding and Crystal Structures
A medium-difficulty quiz on atomic bonding, crystal structures, unit cells, and crystallographic notation. Questions progress from interpreting individual properties to applying and comparing structural concepts.
- Study guide
02 Atomic Bonding and Crystal Structures
Learn how atomic bonding relates to crystal order, how unit cells and Miller indices describe crystals, and how common metal and ceramic structures differ.
- Quiz
04 Mechanical Properties of Materials
A medium-difficulty quiz on how materials respond to stress, deformation, repeated loading, sustained loading, and flaws.
- Flashcards
06 Metals and Alloys
Review how metal structure, alloy composition, processing, heat treatment, and application requirements shape the properties and uses of engineering metals.
- Study guide
06 Metals and Alloys
Learn how metal structure, composition, processing, and heat treatment shape material properties, and how to select an alloy for an engineering application.
- Study guide
7 Engineering Ethics and Responsibility
Learn how engineers apply professional duties, ethical codes, safety practices, and community considerations to responsible engineering decisions.
- Study guide
08 Polymers
Learn how polymer chain structure, molecular-weight distribution, thermal behavior, and processing methods determine the properties and uses of polymer materials.
- Study guide
09 Composite Materials
Learn how composite materials combine constituents, how reinforcement arrangements shape their properties, and how to select them for particular applications.
- Quiz
10 Materials Selection and Design
A medium-difficulty quiz on applying materials-selection principles, evaluating candidates, and accounting for processing and service requirements.