Construction Sequencing and Dependencies Online Quiz Questions

Use this free practice quiz with 20 questions to review Construction Sequencing and Dependencies, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

Which dependency type describes a follow-on task that must wait until its predecessor is complete?

  1. A

    Finish-to-start: the follow-on task waits until its predecessor is complete.

  2. B

    Start-to-start: the follow-on task can begin after its predecessor starts.

  3. C

    Finish-to-finish: two tasks must reach completion together.

  4. D

    Resource or space dependency: tasks compete for a limited resource or work area.

02
Choose all
1 point

Select all statements that correctly describe construction dependencies or concurrent work.

  1. A

    Concurrent work may be planned when crews have sufficient separation, access, and hazard controls.

  2. B

    Tasks competing for a limited hoist have a resource dependency.

  3. C

    In a start-to-start dependency, a follow-on task can begin after its predecessor starts.

  4. D

    In a finish-to-start dependency, two tasks must reach completion together.

03
True or false
1 point

True or false: In a finish-to-start dependency, the follow-on task waits until its predecessor is complete.

  1. A

    True

  2. B

    False

04
Written response
1 point

What dependency type describes a follow-on task that waits until its predecessor is complete?

05
Fill in the blank
1 point

In a finish-to-start dependency, the follow-on task waits until its predecessor is . A dependency can occur when tasks compete for a limited resource or work area.

06
Open ended
1 point

Describe how a team should develop a construction sequence that accounts for activity prerequisites, resource or space dependencies, and possible concurrent work.

07
Choose one
1 point

Before scheduling a ceiling close-in, which condition best indicates that the work is ready to proceed?

  1. A

    Proceed when the scheduled start date is approaching, even if overhead work or inspections are incomplete.

  2. B

    Confirm overhead rough-in is complete, required tests and inspections have passed, deficiencies are resolved, and the area is ready for the next trade.

  3. C

    Close the ceiling first and inspect the concealed work only if a problem is later reported.

  4. D

    Proceed once materials are available, regardless of whether the preceding work is complete.

08
Choose all
1 point

Select all items that can be constraints preventing an activity from being ready to proceed.

  1. A

    Incomplete drawings or decisions.

  2. B

    Unavailable materials.

  3. C

    Blocked access.

  4. D

    An approaching scheduled start date, by itself.

  5. E

    Unresolved inspections.

09
True or false
1 point

True or false: An activity should be treated as ready merely because its scheduled start date is approaching, even if constraints remain unresolved.

  1. A

    True

  2. B

    False

10
Written response
1 point

What planning practice examines upcoming work in greater detail and removes constraints before work is promised for a particular week?

11
Fill in the blank
1 point

Construction activities should be sequenced according to their .

12
Choose one
1 point

Which dependency type means a follow-on task waits until its predecessor is complete?

  1. A

    Finish-to-start

  2. B

    Start-to-start

  3. C

    Finish-to-finish

  4. D

    Resource or space dependency

13
True or false
1 point

True or false: A start-to-start dependency means the follow-on task must wait until its predecessor is complete.

  1. A

    True

  2. B

    False

14
Written response
1 point

What dependency type requires a follow-on task to wait until its predecessor is complete?

15
Choose one
1 point

Which plan is an example of feasible concurrent construction work?

  1. A

    Mechanical rough-in proceeds on one floor while framing continues on another, with separation, access, material movement, falling-object risks, and shared hoist capacity addressed.

  2. B

    Mechanical rough-in and framing proceed in the same area at the same time, without checking access or hazards.

  3. C

    All work is delayed until every activity in the entire project is complete.

  4. D

    A follow-on task begins even though its required predecessor work is unfinished.

16
Written response
1 point

Which dependency type requires two tasks to reach completion together?

17
Choose one
1 point

Two activities need the same hoist during an overlapping period. What type of dependency does this illustrate?

  1. A

    Resource or space dependency

  2. B

    Finish-to-start dependency

  3. C

    Start-to-start dependency

  4. D

    Finish-to-finish dependency

18
Choose one
1 point

Which statement describes a resource or space dependency?

  1. A

    Activities compete for a limited resource or work area, such as a hoist or access route.

  2. B

    A follow-on task waits for its predecessor to finish.

  3. C

    A follow-on task begins after its predecessor starts.

  4. D

    Two tasks must reach completion together.

19
Choose one
1 point

Waterproofing is scheduled to begin only after the concrete surface is ready. What type of dependency does this describe?

  1. A

    The two tasks must finish together.

  2. B

    The follow-on task waits until its predecessor is complete.

  3. C

    The follow-on task begins as soon as its predecessor starts.

  4. D

    The tasks compete for a shared resource or work area.

20
Choose one
1 point

Two crews are scheduled to use the same hoist at the same time. Which dependency should the team address?

  1. A

    A follow-on task must wait for a predecessor to finish.

  2. B

    One task can start after another task begins.

  3. C

    Two crews need the same hoist at the same time.

  4. D

    Two tasks must reach completion together.