What is a construction sequence?

Back

A construction sequence is the planned order and coordination of work so crews have the information, materials, access, and space needed to complete tasks safely and efficiently.

02
Front

How can a project be broken into a workable sequence?

Back

Start with project milestones, divide the work into manageable phases, then break each phase into work areas and activities that can be planned, assigned, and checked.

03
Front

What should determine the order of construction activities?

Back

Sequence activities according to their actual prerequisites, rather than relying only on the order in which they appear in a general schedule.

04
Front

What is a finish-to-start dependency?

Back

In a finish-to-start dependency, the follow-on task waits until its predecessor is complete; for example, waterproofing begins after the concrete surface is ready.

05
Front

What is a start-to-start dependency?

Back

In a start-to-start dependency, a follow-on task can begin after its predecessor starts, often in a separate area; for example, interior rough-in may begin on lower floors while framing continues above.

06
Front

What is a finish-to-finish dependency?

Back

In a finish-to-finish dependency, two tasks must both reach completion before the area is accepted; for example, system installation and required testing.

07
Front

What creates a resource or space dependency?

Back

A resource or space dependency occurs when tasks compete for a limited resource or work area, such as a hoist, loading zone, access route, or ceiling space.

08
Front

Why can a shared hoist affect activity sequencing?

Back

A shared hoist can create a resource dependency: activities needing it may compete for the same limited equipment and require coordination.

09
Front

What conditions make concurrent construction work appropriate?

Back

Concurrent work is appropriate only when crews have sufficient separation, access, and hazard controls.

10
Front

When can mechanical rough-in proceed alongside framing?

Back

Mechanical rough-in may proceed on one floor while framing continues on another if separation, access, material movement, falling-object risks, and shared hoist capacity are addressed.

11
Front

What should a construction schedule show about activity relationships?

Back

A schedule should show both the necessary sequence of activities and feasible parallel work, accounting for the conditions that make concurrent work safe and practical.

12
Front

Why must a sequence account for shared space and access?

Back

Activities may be ready to proceed in sequence but still conflict if they need the same limited area, access route, or equipment at the same time.