What schedule reference should be used to measure project performance?
Construction Schedule Control Online Quiz Questions
Use this free practice quiz with 20 questions to review Construction Schedule Control, test your knowledge, and prepare for your next test or exam.
Select all practices supported for schedule control.
- A
Link the work sequence with crews, materials, equipment, access, inspections, and needed decisions.
- B
Use an approved schedule that reflects the contract scope, milestones, and interfaces between trades and organizations.
- C
Keep the detailed contractor schedule connected to project-level milestones.
- D
Quietly revise the baseline when work slips so the schedule no longer shows the slippage.
- E
Assess proposed changes for their effects on scope, cost, and time.
True or false: Project performance should be measured against the approved schedule baseline, which should not be quietly revised to conceal slippage.
- A
True
- B
False
What approved schedule reference should be used to measure project performance?
Use the approved schedule to measure project performance.
Explain how an approved schedule baseline supports project control and how it should be handled when actual performance diverges from the plan.
Why should the detailed contractor schedule remain connected to project-level milestones?
- A
To allow contractor schedules to replace the project-level milestones.
- B
To make it easier to revise the baseline whenever actual progress differs from the plan.
- C
So field teams and management work to compatible expectations.
- D
So that interfaces between trades and organizations can be omitted from the schedule.
Select all practices consistent with controlling a project schedule and assessing proposed changes.
- A
Consider the proposed change's effects on scope, cost, and time.
- B
Assess only the schedule effect because scope and cost are independent of time.
- C
Compare actual performance with the approved baseline.
- D
Keep contractor-level schedule detail connected to project-level milestones.
- E
Quietly adjust the baseline to remove recorded slippage before assessing the proposed change.
True or false: It is acceptable to quietly revise the approved schedule baseline so that recorded slippage disappears.
- A
True
- B
False
How many interrelated dimensions should be considered when assessing the effects of a proposed change?
Use the approved schedule to measure performance against the plan.
What should be used to measure project performance against the plan?
- A
A revised schedule that removes any recorded slippage
- B
The approved baseline
- C
A list of dates without linked work activities
- D
The latest forecast, used instead of the baseline
It is appropriate to quietly revise the schedule baseline to make project slippage disappear.
- A
True
- B
False
What schedule reference should be used to measure performance against the plan?
When assessing a proposed project change, which impacts should be considered?
- A
Assess only the change's impact on schedule dates
- B
Consider only scope; cost and time are independent
- C
Assess the proposed change's impact on scope, cost, and time
- D
Revise the baseline first, then assess whether the change matters
What does schedule control forecast for the project?
How should the detailed contractor schedule relate to project-level milestones?
- A
Connect the detailed contractor schedule to project-level milestones
- B
Keep the contractor schedule separate from project milestones
- C
Replace project-level milestones with contractor activity dates
- D
Revise milestones whenever actual performance differs from the plan
Which description best captures the role of a construction schedule?
- A
A list of project dates, without links to the work or resources
- B
A cost report that replaces the need to plan work sequence
- C
A record of completed inspections only
- D
A working control tool linking the work sequence and resources needed to complete the project
Which approach provides a sound basis for measuring construction project performance against the plan?
- A
Revise the schedule whenever actual work falls behind
- B
Measure performance against an approved schedule baseline
- C
Use only the project’s final completion date to assess performance
- D
Compare progress with an informal list of planned activities
A project is behind its approved plan. What should the team do with the schedule baseline when measuring performance?
- A
Keep the approved baseline as the reference rather than revising it to conceal slippage
- B
Quietly move baseline dates whenever work falls behind
- C
Replace the baseline with actual dates so there is no difference to measure
- D
Revise the baseline whenever one trade misses a milestone
Related study packs and tools
- Study guide
1 Electrical Quantities and Ohm’s Law
Learn how charge, current, voltage, resistance, power, and energy are related in electric circuits, including how to apply Ohm’s law and interpret worked calculations.
- Flashcards
01 Foundations of Materials Science
Review how processing, structure, properties, and performance connect, and how engineering materials are classified and selected.
- Quiz
1 Vectors for Engineering Mechanics
A medium-difficulty quiz on representing vectors, calculating their components and magnitudes, and applying vector operations in engineering mechanics.
- Quiz
02 Atomic Bonding and Crystal Structures
A medium-difficulty quiz on atomic bonding, crystal structures, unit cells, and crystallographic notation. Questions progress from interpreting individual properties to applying and comparing structural concepts.
- Study guide
02 Atomic Bonding and Crystal Structures
Learn how atomic bonding relates to crystal order, how unit cells and Miller indices describe crystals, and how common metal and ceramic structures differ.
- Quiz
04 Mechanical Properties of Materials
A medium-difficulty quiz on how materials respond to stress, deformation, repeated loading, sustained loading, and flaws.
- Flashcards
06 Metals and Alloys
Review how metal structure, alloy composition, processing, heat treatment, and application requirements shape the properties and uses of engineering metals.
- Study guide
06 Metals and Alloys
Learn how metal structure, composition, processing, and heat treatment shape material properties, and how to select an alloy for an engineering application.
- Study guide
7 Engineering Ethics and Responsibility
Learn how engineers apply professional duties, ethical codes, safety practices, and community considerations to responsible engineering decisions.
- Study guide
08 Polymers
Learn how polymer chain structure, molecular-weight distribution, thermal behavior, and processing methods determine the properties and uses of polymer materials.
- Study guide
09 Composite Materials
Learn how composite materials combine constituents, how reinforcement arrangements shape their properties, and how to select them for particular applications.
- Quiz
10 Materials Selection and Design
A medium-difficulty quiz on applying materials-selection principles, evaluating candidates, and accounting for processing and service requirements.