Construction Schedule Control Online Quiz Questions

Use this free practice quiz with 20 questions to review Construction Schedule Control, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

What schedule reference should be used to measure project performance?

  1. A

    Against whichever schedule was most recently edited, even if it has not been approved.

  2. B

    Against the approved schedule baseline.

  3. C

    Against a separate schedule that is not connected to project milestones.

  4. D

    Against the planned finish date only, without comparing actual performance to the plan.

02
Choose all
1 point

Select all practices supported for schedule control.

  1. A

    Link the work sequence with crews, materials, equipment, access, inspections, and needed decisions.

  2. B

    Use an approved schedule that reflects the contract scope, milestones, and interfaces between trades and organizations.

  3. C

    Keep the detailed contractor schedule connected to project-level milestones.

  4. D

    Quietly revise the baseline when work slips so the schedule no longer shows the slippage.

  5. E

    Assess proposed changes for their effects on scope, cost, and time.

03
True or false
1 point

True or false: Project performance should be measured against the approved schedule baseline, which should not be quietly revised to conceal slippage.

  1. A

    True

  2. B

    False

04
Written response
1 point

What approved schedule reference should be used to measure project performance?

05
Fill in the blank
1 point

Use the approved schedule to measure project performance.

06
Open ended
1 point

Explain how an approved schedule baseline supports project control and how it should be handled when actual performance diverges from the plan.

07
Choose one
1 point

Why should the detailed contractor schedule remain connected to project-level milestones?

  1. A

    To allow contractor schedules to replace the project-level milestones.

  2. B

    To make it easier to revise the baseline whenever actual progress differs from the plan.

  3. C

    So field teams and management work to compatible expectations.

  4. D

    So that interfaces between trades and organizations can be omitted from the schedule.

08
Choose all
1 point

Select all practices consistent with controlling a project schedule and assessing proposed changes.

  1. A

    Consider the proposed change's effects on scope, cost, and time.

  2. B

    Assess only the schedule effect because scope and cost are independent of time.

  3. C

    Compare actual performance with the approved baseline.

  4. D

    Keep contractor-level schedule detail connected to project-level milestones.

  5. E

    Quietly adjust the baseline to remove recorded slippage before assessing the proposed change.

09
True or false
1 point

True or false: It is acceptable to quietly revise the approved schedule baseline so that recorded slippage disappears.

  1. A

    True

  2. B

    False

10
Written response
1 point

How many interrelated dimensions should be considered when assessing the effects of a proposed change?

11
Fill in the blank
1 point

Use the approved schedule to measure performance against the plan.

12
Choose one
1 point

What should be used to measure project performance against the plan?

  1. A

    A revised schedule that removes any recorded slippage

  2. B

    The approved baseline

  3. C

    A list of dates without linked work activities

  4. D

    The latest forecast, used instead of the baseline

13
True or false
1 point

It is appropriate to quietly revise the schedule baseline to make project slippage disappear.

  1. A

    True

  2. B

    False

14
Written response
1 point

What schedule reference should be used to measure performance against the plan?

15
Choose one
1 point

When assessing a proposed project change, which impacts should be considered?

  1. A

    Assess only the change's impact on schedule dates

  2. B

    Consider only scope; cost and time are independent

  3. C

    Assess the proposed change's impact on scope, cost, and time

  4. D

    Revise the baseline first, then assess whether the change matters

16
Written response
1 point

What does schedule control forecast for the project?

17
Choose one
1 point

How should the detailed contractor schedule relate to project-level milestones?

  1. A

    Connect the detailed contractor schedule to project-level milestones

  2. B

    Keep the contractor schedule separate from project milestones

  3. C

    Replace project-level milestones with contractor activity dates

  4. D

    Revise milestones whenever actual performance differs from the plan

18
Choose one
1 point

Which description best captures the role of a construction schedule?

  1. A

    A list of project dates, without links to the work or resources

  2. B

    A cost report that replaces the need to plan work sequence

  3. C

    A record of completed inspections only

  4. D

    A working control tool linking the work sequence and resources needed to complete the project

19
Choose one
1 point

Which approach provides a sound basis for measuring construction project performance against the plan?

  1. A

    Revise the schedule whenever actual work falls behind

  2. B

    Measure performance against an approved schedule baseline

  3. C

    Use only the project’s final completion date to assess performance

  4. D

    Compare progress with an informal list of planned activities

20
Choose one
1 point

A project is behind its approved plan. What should the team do with the schedule baseline when measuring performance?

  1. A

    Keep the approved baseline as the reference rather than revising it to conceal slippage

  2. B

    Quietly move baseline dates whenever work falls behind

  3. C

    Replace the baseline with actual dates so there is no difference to measure

  4. D

    Revise the baseline whenever one trade misses a milestone