Construction Schedule Baselines and Control Free Online Flashcards

Study Construction Schedule Baselines and Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

How does a schedule baseline support project control?

Back

Compare actual performance with the approved baseline to measure progress and control the project.

02
Front

What qualities should a project schedule have before it is used as a baseline?

Back

The schedule should be approved and logically linked, reflecting the contract scope, milestones, and interfaces between trades and organizations.

03
Front

Why connect contractor schedule details to project-level milestones?

Back

Keep the contractor’s detailed schedule connected to project-level milestones so field teams and management work to compatible expectations.

04
Front

How should teams handle the baseline when actual work falls behind?

Back

Measure performance against the approved baseline; do not quietly revise it to make schedule slippage disappear.

05
Front

What does a construction schedule link as a working control tool?

Back

A construction schedule is a working control tool that links the work sequence, crews, materials, equipment, access, inspections, and decisions.

06
Front

What provides the reference for comparing actual performance with the plan?

Back

An approved baseline gives the team a stable reference for comparing actual project performance with the plan.

07
Front

Which three project factors should be considered when assessing a proposed change?

Back

Proposed changes should be assessed for their effects on scope, cost, and time because these factors affect one another.

08
Front

What project information should an approved schedule baseline reflect?

Back

The baseline should reflect the contract scope, project milestones, and interfaces between trades and organizations.

09
Front

What does comparing actual performance with the baseline reveal?

Back

Use the baseline to measure performance and identify when actual results diverge from the plan.

10
Front

What does logical linkage in a project schedule help represent?

Back

A logically linked schedule represents the work sequence and the interfaces between trades and organizations.

11
Front

What should connect contractor-level schedule detail with project-level expectations?

Back

Keep the contractor-level schedule connected to project-level milestones so field teams and management share compatible expectations.

12
Front

Why should teams avoid quietly revising the baseline after slippage?

Back

Do not alter the approved baseline simply to conceal slippage; use it to measure performance against the plan.