5 Risk Registers and Ongoing Monitoring Online Quiz Questions

Use this free practice quiz with 20 questions to review 5 Risk Registers and Ongoing Monitoring, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

Consider the risk statement: “Because late design approval may delay procurement, equipment may arrive after installation begins, disrupting commissioning.” Which part states the possible effect?

  1. A

    Late design approval

  2. B

    Equipment may arrive after installation begins

  3. C

    Commissioning is disrupted

02
Choose one
1 point

Which entry is the most specific, observable trigger for a possible supplier delay?

  1. A

    The supplier may be late

  2. B

    Supplier has not confirmed shipment by 15 May

  3. C

    The shipment could cause problems

03
Choose one
1 point

A project has a high-exposure risk whose conditions are changing quickly. Which review approach best fits the guidance?

  1. A

    Review it frequently because its exposure is high and changing quickly

  2. B

    Review it only at project close because it is already documented

  3. C

    Use the same infrequent schedule for every risk

04
Choose one
1 point

A project assigns one person to oversee a risk while another completes a particular response task. What is the role of the person overseeing the risk?

  1. A

    The person assigned to complete every response task

  2. B

    The person accountable for monitoring the risk and coordinating its response

  3. C

    The person who records meeting minutes

05
Choose all
1 point

During a scheduled risk review, which practices support a meaningful reassessment? Select all that apply.

  1. A

    Check whether existing risks are still valid and whether new risks have emerged

  2. B

    Change rating criteria each time to make the latest assessment look more favorable

  3. C

    Check whether triggers are near or reached and whether actions are on track

  4. D

    Use the same agreed criteria to reassess likelihood and impact

06
Choose all
1 point

A project lead is preparing a risk update to help decision-makers act. Which information should the update emphasize? Select all that apply.

  1. A

    Summarize significant risks and changes in exposure

  2. B

    Identify triggers reached or approaching and overdue or ineffective responses

  3. C

    Repeat every register entry without highlighting changes or decisions

  4. D

    State decisions needed and risks that exceed agreed tolerance

07
True or false
1 point

When a risk occurs, the actual problem should be managed as an issue, while any remaining uncertainty may still be tracked as a risk.

  1. A

    True

  2. B

    False

08
True or false
1 point

A project team only needs to review risks at planned intervals, even when significant changes occur between reviews.

  1. A

    True

  2. B

    False

09
Written response
1 point

What is the shared project record called when it brings together uncertainties, potential effects, assessments, owners, and planned responses?

10
Written response
1 point

Which register field indicates whether a risk’s exposure is rising, stable, or falling?

11
Fill in the blank
1 point

When using the project’s agreed rating scale, a risk register commonly records likelihood, impact, and .

12
Fill in the blank
1 point

To make a response action trackable, record an owner and a for the action.

13
Open ended
1 point

A response action is overdue, and monitoring shows that it has not reduced the risk exposure. What should the team do next, and when might escalation be appropriate?

14
Choose one
1 point

A project manager records: “Because supplier qualification is incomplete, a shipment may arrive late, delaying system testing.” Which option correctly identifies the cause, uncertain event, and possible effect, in that order?

  1. A

    Cause: testing is delayed; event: qualification is incomplete; effect: shipment may arrive late.

  2. B

    Cause: qualification is incomplete; event: shipment may arrive late; effect: system testing may be delayed.

  3. C

    Cause: shipment may arrive late; event: testing is delayed; effect: qualification is incomplete.

  4. D

    Cause: qualification is incomplete; event: system testing is delayed; effect: shipment may arrive late.

15
Choose one
1 point

A team wants a trigger for the risk that a software integration may fail. Which proposed trigger is most specific and checkable?

  1. A

    The integration could be difficult.

  2. B

    The software team is concerned about integration.

  3. C

    A required integration test fails on two consecutive runs.

  4. D

    Integration problems may occur near launch.

16
True or false
1 point

When a risk happens, record and manage the actual problem as an issue, while retaining any remaining uncertainty as a risk if appropriate.

  1. A

    True

  2. B

    False

17
Choose one
1 point

A response plan has one person coordinating the overall response and several people assigned individual tasks. Which description correctly distinguishes the roles?

  1. A

    The risk owner oversees the risk and coordinates its response; action owners complete assigned tasks.

  2. B

    The action owner oversees the risk; the risk owner completes every task in the response.

  3. C

    The risk owner records the risk; action owners decide whether it should be escalated.

  4. D

    The risk owner and action owners are interchangeable roles with the same responsibilities.

18
Written response
1 point

What risk-register field summarizes whether exposure is rising, stable, or falling?

19
Choose one
1 point

A project has some high-exposure risks that can change quickly and some lower-exposure risks that are relatively stable. How should the team set review frequency?

  1. A

    Review every risk only at project start and close, regardless of changing conditions.

  2. B

    Review high-exposure or fast-changing risks more frequently, and review others less often as appropriate.

  3. C

    Review all risks on the same fixed schedule, even if their exposure and pace differ.

  4. D

    Review a risk only after its trigger has been reached.

20
Written response
1 point

Alongside an owner, what scheduling field should be recorded for each risk-response action?