What does an integrated project plan coordinate?

Back

It coordinates scope, schedule, resources, quality, procurement, and measurement so that the plans agree and guide shared decisions.

02
Front

What is a project planning assumption?

Back

An assumption is a statement treated as true for planning, even though it may prove false. Important assumptions should have an owner and be tracked.

03
Front

What is a project constraint?

Back

A constraint is a limit the team must work within, such as a fixed launch date, spending ceiling, required technology, or limited staff availability.

04
Front

What should a project scope definition specify?

Back

Describe the product, service, or result; define what is included and excluded; and state how each deliverable will be accepted.

05
Front

What is the purpose of a work breakdown structure?

Back

A work breakdown structure breaks work into manageable components, linking estimates, responsibilities, and progress to defined work.

06
Front

What belongs in a realistic project schedule?

Back

A realistic schedule sequences activities, estimates durations, identifies dependencies, and sets milestones. It also includes reviews, testing, approvals, and procurement lead times.

07
Front

What should resource planning establish for each activity?

Back

Identify the people, skills, equipment, facilities, and funding needed for each activity. Confirm availability and resolve over-allocation.

08
Front

What should a quality plan define for each deliverable?

Back

For each deliverable, define measurable quality criteria, verification methods, responsible reviewers, and acceptance authority.

09
Front

How should quality activities be incorporated into a plan?

Back

Quality activities such as inspections, tests, and peer reviews belong in the schedule and require resources.

10
Front

What should procurement planning cover?

Back

Plan requirements, selection criteria, approvals, contract or order milestones, delivery dates, and how supplier performance and deliverables will be checked.

11
Front

What information should be specified for each project measure?

Back

Specify each measure's definition, target or tolerance, data source, collection frequency, and owner.

12
Front

What does a measurement baseline connect?

Back

A measurement baseline connects authorized scope, schedule, and cost for tracking execution.