3 Scope and Requirements Management Online Quiz Questions

Use this free practice quiz with 20 questions to review 3 Scope and Requirements Management, test your knowledge, and prepare for your next test or exam.

20 questions
01
True or false
1 point

True or false: Project scope describes the work and results a project is authorized to deliver, while requirements explain what stakeholders need from those results.

  1. A

    True

  2. B

    False

02
Choose one
1 point

Which requirement is most clearly testable?

  1. A

    The system should be user-friendly.

  2. B

    The system shall allow a user to reset a password by email.

  3. C

    The system should be modern.

  4. D

    The system should satisfy everyone.

03
Written response
1 point

What is the process of discovering stakeholder needs and constraints called?

04
Fill in the blank
1 point

A distinct, reviewable result produced by a project is called a .

05
Choose one
1 point

A project team needs to organize its approved scope into manageable components. Which description best fits a work breakdown structure (WBS)?

  1. A

    The sequence and dates for completing project activities.

  2. B

    A list of stakeholder preferences that have not been approved.

  3. C

    A hierarchical breakdown of authorized scope into deliverables and manageable work packages.

  4. D

    A report of project costs after the work is complete.

06
Choose all
1 point

Which statements accurately describe a WBS? Select all that apply.

  1. A

    It should cover the complete agreed scope.

  2. B

    It primarily specifies the sequence and dates for producing deliverables.

  3. C

    It includes project-management work as well as product work.

  4. D

    It decomposes the scope into deliverables and manageable work packages.

07
True or false
1 point

True or false: Once the scope baseline is approved, a team may begin a small requested addition without change control if the addition seems useful.

  1. A

    True

  2. B

    False

08
Fill in the blank
1 point

In the change-control process, the step that assesses the effects of a requested change before a decision is made is called .

09
Written response
1 point

What does the abbreviation WBS stand for in project scope management?

10
Choose one
1 point

A project will launch an online store but will not provide ongoing product photography or post-launch marketing. How should the team use this information to clarify scope?

  1. A

    A list of tasks that the team has already completed.

  2. B

    A statement that ongoing product photography and post-launch marketing are outside the online-store project.

  3. C

    A priority ranking for the requirements of the online store.

  4. D

    An acceptance test for the checkout function.

11
Choose all
1 point

Which details should be recorded for each requirement to support identification, traceability, prioritization, and verification? Select all that apply.

  1. A

    An identifier for the requirement.

  2. B

    The source of the requirement.

  3. C

    Its priority.

  4. D

    The date on which the project team expects to complete it.

  5. E

    A way to verify the requirement.

12
Open ended
1 point

A stakeholder asks to add saved payment methods to an online store after its scope has been baselined. Explain how the team should handle the request before and after a decision is made.

13
Choose one
1 point

A team wants to clarify what a particular WBS element includes, who is responsible for it, and how its completion will be judged. What should the WBS dictionary describe?

  1. A

    Only the project’s final cost and actual completion date.

  2. B

    The preferences of every stakeholder, including those unrelated to the project.

  3. C

    Each element’s boundaries, owner, and acceptance conditions.

  4. D

    A guaranteed list of all future change requests.

14
True or false
1 point

True or false: A WBS should include project-management work as well as the work that produces the project’s product.

  1. A

    True

  2. B

    False

15
Choose one
1 point

A project team wants to replace a vague requirement with one that can be verified. Which requirement is the most directly testable?

  1. A

    The system shall allow a user to reset a password by email.

  2. B

    The system should be user-friendly.

  3. C

    The system should feel modern.

  4. D

    The system should be fast whenever possible.

16
Choose one
1 point

A team is eliciting requirements for a new service platform. It has consulted end users and the sponsor, but not the support technicians who will operate and maintain the platform. What is the best next step?

  1. A

    Consult only the project sponsor, because the sponsor approves the work.

  2. B

    Include support technicians who will operate and maintain the system.

  3. C

    Consult only end users, because they will use the system directly.

  4. D

    Wait until the system is built, then ask support technicians to review it.

17
Choose one
1 point

A reviewer wants to trace a documented requirement back to the stakeholder need that prompted it. Which requirement-record field is most directly useful?

  1. A

    The requirement's priority

  2. B

    The proposed implementation sequence

  3. C

    The requirement's source

  4. D

    The name of the project schedule

18
Choose one
1 point

An online-store project includes product listings, checkout, and staff training, but not ongoing product photography. Which statement would best clarify that project boundary?

  1. A

    The storefront will include a shopping cart.

  2. B

    Staff will receive training before handover.

  3. C

    The checkout must meet its acceptance criteria.

  4. D

    Ongoing product photography is not included in the project.

19
Written response
1 point

What is the standard term for the approved scope definition together with its supporting WBS, used as the reference for evaluating proposed changes?

20
Written response
1 point

A stakeholder proposes a change after the scope baseline has been approved. What is the first action in the agreed change-control process?