01
Front

What does project scope define?

Back

Project scope describes the work and results the project is authorized to deliver.

02
Front

What do project requirements describe?

Back

Requirements explain what stakeholders need from the project’s results.

03
Front

Name several methods for eliciting requirements.

Back

Methods include interviews, workshops, observation, document review, surveys, and prototypes.

04
Front

Whose needs should requirements elicitation include?

Back

Involve people who will use, approve, operate, maintain, or be affected by the result; their expectations may differ.

05
Front

What information should a requirement record include?

Back

Record an identifier, description, source, priority, rationale, and a way to verify each requirement.

06
Front

What makes a requirement more testable?

Back

State a specific, testable outcome, such as allowing a user to reset a password by email, rather than saying the system should be user-friendly.

07
Front

What should stakeholder review check about requirements?

Back

Check that requirements are necessary, feasible, consistent, and verifiable.

08
Front

What is a project deliverable?

Back

A deliverable is a distinct, reviewable project result, such as an approved design or training materials.

09
Front

Why define acceptance criteria for deliverables?

Back

Acceptance criteria let the team and customer judge whether a major deliverable is complete.

10
Front

What do project exclusions clarify?

Back

Exclusions identify work or results stakeholders might assume are included but that are outside the agreed project scope.

11
Front

What is a work breakdown structure (WBS)?

Back

A WBS hierarchically decomposes the project’s total authorized scope into deliverables and manageable work packages.

12
Front

What does a WBS organize—and what does it not organize?

Back

A WBS organizes what must be produced, not the sequence or dates for producing it.