What does project resource planning establish?
Resource planning identifies what resources a project needs, when they are needed, and who will provide or use them, while checking that plans fit realistic availability.
Study 5 Resource Planning and Management with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.
What does project resource planning establish?
Resource planning identifies what resources a project needs, when they are needed, and who will provide or use them, while checking that plans fit realistic availability.
How do effort and duration differ?
Effort is the amount of work; duration is the elapsed time to complete it. They are related but not interchangeable.
What should be checked when assessing resource availability?
Check commitments, maintenance, leave, delivery lead times, and other constraints. A listed resource may not be available whenever the project needs it.
Why might a person listed at full capacity have less project time available?
A person listed at full capacity may still have meetings, operational duties, or other assignments that reduce usable project time.
What is a resource breakdown structure?
A resource breakdown structure groups resource needs by category, such as personnel, equipment, materials, and facilities.
What does a time-phased resource plan show?
It shows the quantities of resources needed in each period, helping reveal demand peaks and shortages.
How does a named assignment differ from a role-based estimate?
A role-based estimate identifies the capability needed; a named assignment identifies a specific person and should be confirmed before it is relied on in a committed schedule.
What does a responsibility assignment matrix connect?
A responsibility assignment matrix links project work to the people or roles responsible for it.
In RACI, what does the Responsible role do?
The Responsible role performs the work.
In RACI, what does the Accountable role own?
The Accountable role owns the result or decision. Normally, each activity should have one clear accountable role.
How do Consulted and Informed roles differ in RACI?
Consulted roles provide input before or during the work; Informed roles receive updates.
What is resource smoothing?
Resource smoothing moves work within its available schedule flexibility to reduce demand peaks, while keeping the planned completion date unchanged when possible.
Learn how AWS usage, service configuration, and purchasing choices shape costs, and how to estimate a workload’s billable usage.
A medium-difficulty quiz on applying AWS pricing fundamentals to workload choices and cost estimates.
Learn how AWS EC2 pricing and tenancy options balance cost, commitment, flexibility, interruption risk, capacity, and hardware control.
Assess how to match AWS EC2 pricing and hardware options to workload predictability, interruption tolerance, capacity needs, and hardware requirements.
Compare EC2 pricing and hardware options by commitment, flexibility, interruption risk, capacity needs, and host-level control.
Learn how to estimate AWS workload costs, monitor budgets, organize charges with tags, and choose billing reports for cost analysis.
A medium-difficulty quiz on estimating AWS workload costs, monitoring budgets, organizing cost data, and choosing billing reports.
Learn how AWS organizations, billing tools, cost allocation, and monitoring features help teams understand and control cloud spending.
A medium-difficulty quiz on AWS billing, cost allocation, cost analysis, and cost-control tools.
Learn how to compare AWS Support plans, choose cost-management tools, and make informed workload pricing decisions.
A medium-difficulty quiz on choosing AWS Support plans, estimating and monitoring costs, and applying cost-management tools to practical scenarios.
Learn how AWS pricing choices, support plans, billing tools, and cost-allocation practices help forecast, monitor, investigate, and manage cloud spending.