What does a project schedule translate approved scope into?
It translates approved scope into a time-based plan showing the work, its order and expected duration, and planned start and finish dates.
Study 4 Schedule Planning and Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.
What does a project schedule translate approved scope into?
It translates approved scope into a time-based plan showing the work, its order and expected duration, and planned start and finish dates.
What makes a project activity sufficiently well defined?
An activity should be defined clearly enough to estimate, assign, track, and determine when it is complete.
How does activity duration differ from effort?
Duration is the working time an activity is expected to take, not necessarily its effort. Adding people may not shorten work that cannot be divided efficiently and can add coordination overhead.
How is a common three-point expected duration calculated?
A common weighted estimate is 6O+4M+P, where O is optimistic, M most likely, and P pessimistic duration. For 2, 4, and 8 days, it is about 4.3 days.
What does a finish-to-start dependency require?
In a finish-to-start relationship, the successor cannot start until the predecessor finishes.
How do a lead and a lag affect activity sequencing?
A lead allows activities to overlap; a lag requires a waiting interval. Both should represent real work or waiting, not conceal missing activities or unrealistic logic.
How does the forward pass calculate earliest dates?
Move forward through the network: for a simple finish-to-start activity, EF=ES+duration. Its earliest start is the latest earliest finish among its predecessors.
What does total float measure?
Total float is LS−ES, equivalently LF−EF. It is the time an activity can slip without delaying the calculated project finish, given the schedule logic and constraints.
What is the critical path?
It is the longest-duration path through the network and determines the earliest possible project completion under the modeled logic. In the basic example, critical activities have zero total float.
In the example network, which path is critical and when can the project finish?
The critical path is A–C–D–E, and the earliest planned completion is 13 working days after the project starts.
What is the purpose of a schedule baseline?
The approved schedule baseline is the reference for comparing actual progress and current forecasts. It should not be silently changed to hide a forecast delay.
What should happen before a proposed schedule change revises the baseline?
Assess effects on dependencies, milestones, the critical path, finish date, resources, cost, risks, and deliverables. Obtain approval through change control before revising the baseline, then document and communicate the decision and forecast.
Learn how AWS usage, service configuration, and purchasing choices shape costs, and how to estimate a workload’s billable usage.
A medium-difficulty quiz on applying AWS pricing fundamentals to workload choices and cost estimates.
Learn how AWS EC2 pricing and tenancy options balance cost, commitment, flexibility, interruption risk, capacity, and hardware control.
Assess how to match AWS EC2 pricing and hardware options to workload predictability, interruption tolerance, capacity needs, and hardware requirements.
Compare EC2 pricing and hardware options by commitment, flexibility, interruption risk, capacity needs, and host-level control.
Learn how to estimate AWS workload costs, monitor budgets, organize charges with tags, and choose billing reports for cost analysis.
A medium-difficulty quiz on estimating AWS workload costs, monitoring budgets, organizing cost data, and choosing billing reports.
Learn how AWS organizations, billing tools, cost allocation, and monitoring features help teams understand and control cloud spending.
A medium-difficulty quiz on AWS billing, cost allocation, cost analysis, and cost-control tools.
Learn how to compare AWS Support plans, choose cost-management tools, and make informed workload pricing decisions.
A medium-difficulty quiz on choosing AWS Support plans, estimating and monitoring costs, and applying cost-management tools to practical scenarios.
Learn how AWS pricing choices, support plans, billing tools, and cost-allocation practices help forecast, monitor, investigate, and manage cloud spending.