A supplier has already missed a delivery date, and the delay may affect the project. Is this an issue rather than a risk?
8 Project Measurement, Control, and Closeout Online Quiz Questions
Use this free practice quiz with 20 questions to review 8 Project Measurement, Control, and Closeout, test your knowledge, and prepare for your next test or exam.
A project team collects actual performance data and compares it with the plan, but does not use the comparison to make decisions. Has the team carried out project control?
- A
True
- B
False
A project manager may update the project baseline as soon as a change is proposed, provided the change is recorded for later review.
- A
True
- B
False
A team compares actual results with the baseline and uses the differences to decide whether corrective action or a revised forecast is needed. Which project activity is the team carrying out?
- A
Monitoring, because the team is deciding what to do with performance information.
- B
Control, because the team is using performance information to decide whether action is needed.
- C
Closeout, because any comparison with a plan takes place after delivery.
- D
Benefits tracking, because the team is measuring intended outcomes.
A stakeholder proposes adding a deliverable that could affect cost, schedule, and quality. What should the project team do first as it manages this proposed change?
- A
Change the baseline immediately, then ask the team to estimate the effects.
- B
Ask the requester to update the schedule and budget, then notify stakeholders.
- C
Record the request, assess its impacts, obtain an authorized decision, and update plans only if approved.
- D
Defer all assessment until project closeout so the original baseline remains untouched.
A project lead wants to detect whether deliverable quality is falling below expectations. Which measure is most useful for that decision?
- A
Count every email sent, even if the count does not support a project decision.
- B
Compare defects and rework with the quality criteria agreed for the project.
- C
Report a status color without defining what each color means.
- D
Count staff meetings instead of checking whether deliverables meet acceptance criteria.
A project team is improving its risk and issue log. Select all the practices that would help it keep these items visible and manage them as conditions change.
- A
Assign an owner to each risk and issue.
- B
Record impacts and planned responses.
- C
Keep the log unchanged once it has been created.
- D
Set a review date and reassess priority as conditions change.
- E
Escalate items whose impact exceeds the team's authority or agreed tolerance.
A project manager is preparing a status report so stakeholders can make timely decisions. Select all the report elements that support that purpose.
- A
State the overall status and reporting period.
- B
Show progress against objectives and the baseline, supported by evidence.
- C
Present forecasts as confirmed facts so stakeholders can act without uncertainty.
- D
Report significant variances, trends, and forecast completion.
- E
Identify key risks, issues, response owners, and decisions or support needed, including by whom and when.
By the reporting date, 8 of 10 planned deliverables have been accepted. Report the accepted proportion as 108= rather than saying only “mostly complete.”
A project is closing before its intended benefits can be assessed. Assign a named and agree how and when those benefits will be reviewed.
A supplier has already missed a delivery, so the project team must manage the problem that has occurred. What project-management term describes this kind of item?
For a project, EV=80,000 and AC=90,000. Using cost variance =EV−AC, calculate the signed cost variance. Enter the amount in dollars without commas; the fixed dollar sign is supplied.
A project team wants its experience to improve future projects rather than produce a list of observations that no one uses. Describe how the team should capture and handle lessons learned during the work and at closure.
A team is setting up project measures before work begins. Which approach is most likely to make those measures useful for decisions?
- A
Choose whichever project numbers are easiest to collect, then decide how to interpret them later.
- B
Define what the measure means, how it is calculated, who provides the data, how often it is updated, and its attention threshold.
- C
Track only measures that can be expressed as a percentage.
- D
Use the same update frequency for every measure, regardless of its purpose.
At the reporting date, 8 of 10 planned deliverables are accepted, and the remaining two are on the critical path. What is the clearest report of this progress?
- A
Report that the project is mostly complete, since most deliverables have been accepted.
- B
Report only that two deliverables remain, without describing their schedule significance.
- C
Report 80% accepted and state that the remaining deliverables are on the critical path.
- D
Report 100% progress because the team has completed most of the planned work.
What project-management term describes an uncertain event that could affect project objectives?
A project manager estimates that completion will occur later than the baseline date. How should the manager present this information in a status report?
- A
Label the expected completion date as a forecast and distinguish it from observed results.
- B
Present the expected completion date as a fact so that stakeholders have one clear date.
- C
Omit the completion estimate until the project has finished.
- D
Replace the approved baseline date with the current estimate in every report.
A project team has sent all deliverable files to the receiving team. What additional check best confirms that the handoff is complete?
- A
Send the deliverable files and close the project once transmission is confirmed.
- B
Transfer responsibility for the deliverable without checking whether the recipient has access to support.
- C
Wait until every expected benefit has been realized before handing over the deliverable.
- D
Confirm the recipient can operate or maintain the deliverable and knows where to get help.
A team wants its lessons to help both the current project and future teams. Which practice best supports that goal?
- A
Wait until project closure, then record only successes.
- B
Capture lessons throughout the work and record actionable findings with enough context for future use.
- C
Record lessons only when a project has failed to meet its objectives.
- D
Keep lessons within the project team and discard them at closure.
A project has earned value EV=$80,000 and actual cost AC=$90,000. Using cost variance =EV−AC, what is the signed cost variance in dollars? Enter a negative value if the variance is below zero.
Related study packs and tools
- Flashcards
1 AWS Pricing Fundamentals
Learn how AWS usage, service configuration, and purchasing choices shape costs, and how to estimate a workload’s billable usage.
- Quiz
1 AWS Pricing Fundamentals
A medium-difficulty quiz on applying AWS pricing fundamentals to workload choices and cost estimates.
- Flashcards
2 AWS Pricing Models
Learn how AWS EC2 pricing and tenancy options balance cost, commitment, flexibility, interruption risk, capacity, and hardware control.
- Quiz
2 AWS Pricing Models
Assess how to match AWS EC2 pricing and hardware options to workload predictability, interruption tolerance, capacity needs, and hardware requirements.
- Study guide
2 AWS Pricing Models
Compare EC2 pricing and hardware options by commitment, flexibility, interruption risk, capacity needs, and host-level control.
- Flashcards
3 AWS Cost Estimation and Management
Learn how to estimate AWS workload costs, monitor budgets, organize charges with tags, and choose billing reports for cost analysis.
- Quiz
3 AWS Cost Estimation and Management
A medium-difficulty quiz on estimating AWS workload costs, monitoring budgets, organizing cost data, and choosing billing reports.
- Flashcards
4 AWS Billing and Cost Analysis Tools
Learn how AWS organizations, billing tools, cost allocation, and monitoring features help teams understand and control cloud spending.
- Quiz
4 AWS Billing and Cost Analysis Tools
A medium-difficulty quiz on AWS billing, cost allocation, cost analysis, and cost-control tools.
- Flashcards
5 AWS Support Plans and Cost-Management Practice
Learn how to compare AWS Support plans, choose cost-management tools, and make informed workload pricing decisions.
- Quiz
5 AWS Support Plans and Cost-Management Practice
A medium-difficulty quiz on choosing AWS Support plans, estimating and monitoring costs, and applying cost-management tools to practical scenarios.
- Study guide
5 AWS Support Plans and Cost-Management Practice
Learn how AWS pricing choices, support plans, billing tools, and cost-allocation practices help forecast, monitor, investigate, and manage cloud spending.