What does a project schedule show?

Back

A time-based model of the work needed to deliver a project, showing activities, durations, dependencies, milestones, and planned dates.

02
Front

What makes an activity well defined?

Back

Each activity should describe a clear, assignable, estimable, and trackable piece of work, such as “Draft user guide.”

03
Front

What does a project milestone mark?

Back

A milestone marks a significant event or decision and usually has zero duration.

04
Front

How are a predecessor and successor related?

Back

A predecessor must occur before a successor can start or finish.

05
Front

What does a finish-to-start dependency mean?

Back

The successor starts only after the predecessor finishes.

06
Front

What does the critical path determine?

Back

The critical path is the longest chain of dependent activities and determines the earliest possible project finish. A delay on it can delay the whole project.

07
Front

What is float, and how much float does activity B have?

Back

Float is time an activity can slip without delaying a specified successor or project finish. In the launch example, activity B has one day of float.

08
Front

What does an activity’s duration measure?

Back

Duration is the working time expected to complete an activity; it is not necessarily the total elapsed time between its start and finish.

09
Front

What is parametric estimating?

Back

Apply a rate to a quantity, such as hours per unit, to estimate the activity duration.

10
Front

How does analogous estimating work?

Back

Use the duration of a comparable past activity, adjusted for differences.

11
Front

What does each view emphasize: a Gantt chart and a network diagram?

Back

A Gantt chart shows activities as bars across a timeline; a network diagram emphasizes dependencies and paths.

12
Front

What is the schedule baseline used for?

Back

The baseline is the approved reference plan used to assess progress and changes. Approved changes should be controlled and documented.