A team is documenting a possible supplier delay. Which description structure will best support assessing the risk and choosing a targeted response?
5 Project Risk Management Online Quiz Questions
Use this free practice quiz with 20 questions to review 5 Project Risk Management, test your knowledge, and prepare for your next test or exam.
True or false: A team should define its probability and impact rating scales and priority thresholds before using them to rank risks.
- A
True
- B
False
A risk register lists a possible equipment failure. The equipment has now failed. What should the team do with this event?
- A
Treat it as an issue to manage.
- B
Keep it classified as a future risk until project closure.
- C
Remove it from the register without follow-up.
- D
Classify it as an opportunity because it is now certain.
A project delay has a 25% chance of causing $36,000 in costs. Using EMV=probability×monetary impact, what is its expected monetary value?
- A
$9,000
- B
$27,000
- C
$36,000
- D
$144,000
A project team wants to address a threat without changing the plan to eliminate it. Which two actions are examples of mitigating or transferring/sharing the threat?
- A
Qualify a backup supplier to reduce the likelihood or impact of disruption.
- B
Change the project plan so the threat can no longer affect it.
- C
Use an agreement or insurance to shift or distribute some exposure.
- D
Take no proactive action and monitor the risk.
To make responsibility for follow-up explicit, a risk register should identify an for each risk.
A previously uncertain event has occurred and now requires management. What is the risk-management term for it?
A project team has identified a beneficial opportunity. Which two strategies actively seek to secure or increase that benefit?
- A
Accept the opportunity without special action.
- B
Exploit the opportunity to ensure it occurs.
- C
Avoid the opportunity by changing the plan so it cannot happen.
- D
Enhance the opportunity’s likelihood or benefit.
During monitoring, the team should look for that remain after a response has been implemented.
A risk has a 15% probability of causing $60,000 in additional costs. Using EMV=probability×monetary impact, what is its EMV in dollars?
True or false: Risk management is iterative because monitoring can reveal new risks or show that existing plans need to change.
- A
True
- B
False
A team redesigns a planned activity so that a specific threat can no longer affect project objectives. Which threat response strategy is it using?
- A
Mitigate the threat by reducing its likelihood.
- B
Accept the threat and monitor it.
- C
Avoid the threat by changing the plan so it cannot affect the project.
- D
Transfer some exposure through an agreement.
A supplier misses a production milestone, and the delay is already postponing system testing. How should the team classify the missed milestone and its consequences?
- A
A new risk
- B
An issue
- C
A residual risk
- D
An opportunity
True or false: A project risk can be an uncertain future event that may benefit the project, not only one that may cause harm.
- A
True
- B
False
A team describes a risk as follows: “Because the supplier has limited production capacity, a critical component may arrive late, delaying system testing.” Which phrase names the uncertain event?
- A
The supplier has limited production capacity
- B
System testing is delayed
- C
The component may arrive late
- D
The project has a critical component
A project team qualifies a backup supplier so it can reduce the disruption caused by a possible failure of its primary supplier. Which threat response strategy is this?
- A
Accept the threat
- B
Mitigate the threat
- C
Avoid the threat
- D
Transfer the threat
A project team will rate risks using probability and impact scales. What should it do first to make ratings and prioritization consistent across the team?
- A
Let each team member choose personal rating definitions
- B
Rank risks by impact alone
- C
Agree on rating definitions and priority thresholds before assessing risks
- D
Use quantitative analysis for every identified risk
A project delay has a 30% chance of causing $40,000 in costs. Using EMV=probability×monetary impact, what is the expected monetary value in dollars? Enter the amount as a number, without a currency symbol or commas.
A team will order from a qualified backup supplier if the primary supplier’s production milestone slips past a defined threshold. What risk-register field records the condition that prompts this action?
A project team is concerned that a critical component may arrive late and has qualified a backup supplier. Draft a concise response plan stating what the team will do, who owns the action, when it will be done, what resources it requires, and the condition that will trigger it.