5 Project Risk Management Online Quiz Questions

Use this free practice quiz with 20 questions to review 5 Project Risk Management, test your knowledge, and prepare for your next test or exam.

20 questions
01
Choose one
1 point

A team is documenting a possible supplier delay. Which description structure will best support assessing the risk and choosing a targeted response?

  1. A

    A list of the project’s objectives, owners, and approval dates

  2. B

    A cause, an uncertain event, and a possible effect

  3. C

    A response action, its cost, and the date it was completed

  4. D

    A category, priority, and current status

02
True or false
1 point

True or false: A team should define its probability and impact rating scales and priority thresholds before using them to rank risks.

  1. A

    True

  2. B

    False

03
Choose one
1 point

A risk register lists a possible equipment failure. The equipment has now failed. What should the team do with this event?

  1. A

    Treat it as an issue to manage.

  2. B

    Keep it classified as a future risk until project closure.

  3. C

    Remove it from the register without follow-up.

  4. D

    Classify it as an opportunity because it is now certain.

04
Choose one
1 point

A project delay has a 25% chance of causing $36,000 in costs. Using EMV=probability×monetary impact\text{EMV} = \text{probability} \times \text{monetary impact}, what is its expected monetary value?

  1. A

    $9,000

  2. B

    $27,000

  3. C

    $36,000

  4. D

    $144,000

05
Choose all
1 point

A project team wants to address a threat without changing the plan to eliminate it. Which two actions are examples of mitigating or transferring/sharing the threat?

  1. A

    Qualify a backup supplier to reduce the likelihood or impact of disruption.

  2. B

    Change the project plan so the threat can no longer affect it.

  3. C

    Use an agreement or insurance to shift or distribute some exposure.

  4. D

    Take no proactive action and monitor the risk.

06
Fill in the blank
1 point

To make responsibility for follow-up explicit, a risk register should identify an for each risk.

07
Written response
1 point

A previously uncertain event has occurred and now requires management. What is the risk-management term for it?

08
Choose all
1 point

A project team has identified a beneficial opportunity. Which two strategies actively seek to secure or increase that benefit?

  1. A

    Accept the opportunity without special action.

  2. B

    Exploit the opportunity to ensure it occurs.

  3. C

    Avoid the opportunity by changing the plan so it cannot happen.

  4. D

    Enhance the opportunity’s likelihood or benefit.

09
Fill in the blank
1 point

During monitoring, the team should look for that remain after a response has been implemented.

10
Written response
1 point

A risk has a 15% probability of causing $60,000 in additional costs. Using EMV=probability×monetary impact\text{EMV} = \text{probability} \times \text{monetary impact}, what is its EMV in dollars?

11
True or false
1 point

True or false: Risk management is iterative because monitoring can reveal new risks or show that existing plans need to change.

  1. A

    True

  2. B

    False

12
Choose one
1 point

A team redesigns a planned activity so that a specific threat can no longer affect project objectives. Which threat response strategy is it using?

  1. A

    Mitigate the threat by reducing its likelihood.

  2. B

    Accept the threat and monitor it.

  3. C

    Avoid the threat by changing the plan so it cannot affect the project.

  4. D

    Transfer some exposure through an agreement.

13
Choose one
1 point

A supplier misses a production milestone, and the delay is already postponing system testing. How should the team classify the missed milestone and its consequences?

  1. A

    A new risk

  2. B

    An issue

  3. C

    A residual risk

  4. D

    An opportunity

14
True or false
1 point

True or false: A project risk can be an uncertain future event that may benefit the project, not only one that may cause harm.

  1. A

    True

  2. B

    False

15
Choose one
1 point

A team describes a risk as follows: “Because the supplier has limited production capacity, a critical component may arrive late, delaying system testing.” Which phrase names the uncertain event?

  1. A

    The supplier has limited production capacity

  2. B

    System testing is delayed

  3. C

    The component may arrive late

  4. D

    The project has a critical component

16
Choose one
1 point

A project team qualifies a backup supplier so it can reduce the disruption caused by a possible failure of its primary supplier. Which threat response strategy is this?

  1. A

    Accept the threat

  2. B

    Mitigate the threat

  3. C

    Avoid the threat

  4. D

    Transfer the threat

17
Choose one
1 point

A project team will rate risks using probability and impact scales. What should it do first to make ratings and prioritization consistent across the team?

  1. A

    Let each team member choose personal rating definitions

  2. B

    Rank risks by impact alone

  3. C

    Agree on rating definitions and priority thresholds before assessing risks

  4. D

    Use quantitative analysis for every identified risk

18
Written response
1 point

A project delay has a 30%30\% chance of causing $40,000\$40{,}000 in costs. Using EMV=probability×monetary impact\text{EMV} = \text{probability} \times \text{monetary impact}, what is the expected monetary value in dollars? Enter the amount as a number, without a currency symbol or commas.

19
Written response
1 point

A team will order from a qualified backup supplier if the primary supplier’s production milestone slips past a defined threshold. What risk-register field records the condition that prompts this action?

20
Open ended
1 point

A project team is concerned that a critical component may arrive late and has qualified a backup supplier. Draft a concise response plan stating what the team will do, who owns the action, when it will be done, what resources it requires, and the condition that will trigger it.