5 Project Risk Management Online Quiz Questions
Use this free practice quiz with 20 questions to review 5 Project Risk Management, test your knowledge, and prepare for your next test or exam.
True or false: A team should define its probability and impact rating scales and priority thresholds before using them to rank risks.
- A
True
- B
False
A risk register lists a possible equipment failure. The equipment has now failed. What should the team do with this event?
- A
Treat it as an issue to manage.
- B
Keep it classified as a future risk until project closure.
- C
Remove it from the register without follow-up.
- D
Classify it as an opportunity because it is now certain.
A project delay has a 25% chance of causing $36,000 in costs. Using EMV=probability×monetary impact, what is its expected monetary value?
- A
$9,000
- B
$27,000
- C
$36,000
- D
$144,000
A project team wants to address a threat without changing the plan to eliminate it. Which two actions are examples of mitigating or transferring/sharing the threat?
- A
Qualify a backup supplier to reduce the likelihood or impact of disruption.
- B
Change the project plan so the threat can no longer affect it.
- C
Use an agreement or insurance to shift or distribute some exposure.
- D
Take no proactive action and monitor the risk.
To make responsibility for follow-up explicit, a risk register should identify an for each risk.
A previously uncertain event has occurred and now requires management. What is the risk-management term for it?
A project team has identified a beneficial opportunity. Which two strategies actively seek to secure or increase that benefit?
- A
Accept the opportunity without special action.
- B
Exploit the opportunity to ensure it occurs.
- C
Avoid the opportunity by changing the plan so it cannot happen.
- D
Enhance the opportunity’s likelihood or benefit.
During monitoring, the team should look for that remain after a response has been implemented.
A risk has a 15% probability of causing $60,000 in additional costs. Using EMV=probability×monetary impact, what is its EMV in dollars?
True or false: Risk management is iterative because monitoring can reveal new risks or show that existing plans need to change.
- A
True
- B
False
A team redesigns a planned activity so that a specific threat can no longer affect project objectives. Which threat response strategy is it using?
- A
Mitigate the threat by reducing its likelihood.
- B
Accept the threat and monitor it.
- C
Avoid the threat by changing the plan so it cannot affect the project.
- D
Transfer some exposure through an agreement.
A supplier misses a production milestone, and the delay is already postponing system testing. How should the team classify the missed milestone and its consequences?
- A
A new risk
- B
An issue
- C
A residual risk
- D
An opportunity
True or false: A project risk can be an uncertain future event that may benefit the project, not only one that may cause harm.
- A
True
- B
False
A team describes a risk as follows: “Because the supplier has limited production capacity, a critical component may arrive late, delaying system testing.” Which phrase names the uncertain event?
- A
The supplier has limited production capacity
- B
System testing is delayed
- C
The component may arrive late
- D
The project has a critical component
A project team qualifies a backup supplier so it can reduce the disruption caused by a possible failure of its primary supplier. Which threat response strategy is this?
- A
Accept the threat
- B
Mitigate the threat
- C
Avoid the threat
- D
Transfer the threat
A project team will rate risks using probability and impact scales. What should it do first to make ratings and prioritization consistent across the team?
- A
Let each team member choose personal rating definitions
- B
Rank risks by impact alone
- C
Agree on rating definitions and priority thresholds before assessing risks
- D
Use quantitative analysis for every identified risk
A project delay has a 30% chance of causing $40,000 in costs. Using EMV=probability×monetary impact, what is the expected monetary value in dollars? Enter the amount as a number, without a currency symbol or commas.
A team will order from a qualified backup supplier if the primary supplier’s production milestone slips past a defined threshold. What risk-register field records the condition that prompts this action?
A project team is concerned that a critical component may arrive late and has qualified a backup supplier. Draft a concise response plan stating what the team will do, who owns the action, when it will be done, what resources it requires, and the condition that will trigger it.
Related study packs and tools
- Study guide
2 Process Analysis and Improvement
Learn how to classify processes, map and measure workflow, identify bottlenecks, and test improvements while evaluating the performance of the whole system.
- Quiz
2 Procurement, Sourcing, and Supplier Management
A medium-difficulty quiz on procurement, supplier selection, purchasing controls, negotiation, and responsible sourcing.
- Quiz
03 Employee Selection and Onboarding
A medium-difficulty quiz on applying job-related selection practices, making documented hiring decisions, and planning effective onboarding.
- Flashcards
04 Employee Training and Development
Learn how to identify employee learning needs, design and deliver suitable training, and evaluate its effects on learning and workplace performance.
- Study guide
04 Employee Training and Development
Learn how to identify employee development needs, design and deliver suitable training, and evaluate whether learning transfers to work.
- Quiz
05 Performance Management
A medium-difficulty quiz on setting useful goals, giving feedback, choosing appraisal methods, and responding to performance gaps.
- Quiz
6 Inventory Management
A 14-question quiz on inventory management concepts, replenishment, inventory control, and practical decision-making.
- Study guide
6 Transportation Management
Learn how to select transportation modes and carriers, plan shipments, compare total logistics costs, and measure transportation performance.
- Flashcards
07 Employee Relations
Review the principles and practices that support effective communication, employee engagement, fair conflict resolution, and collective labor relations.
- Study guide
07 Employee Relations
Learn how communication, employee voice, engagement, conflict resolution, and collective labor relations contribute to effective workplace relationships.
- Study guide
8 Supply Chain Management
Learn how supply chain design, sourcing, logistics, coordination, and resilience work together to serve customers while balancing cost, speed, quality, service, and risk.
- Study guide
9 Integrated Operational Decision Making
Learn how forecasting, process design, capacity, inventory, scheduling, quality, and supply-chain choices interact—and how to evaluate them together.