Which description best fits a project schedule milestone?
3 Project Scheduling and Time Management Online Quiz Questions
Use this free practice quiz with 20 questions to review 3 Project Scheduling and Time Management, test your knowledge, and prepare for your next test or exam.
After a project schedule is approved, what is the baseline used for?
- A
A list of tasks that do not have assigned durations
- B
A forecast that replaces the approved plan at every status meeting
- C
The approved reference plan against which progress and changes are assessed
- D
A chart that displays activities as bars across a timeline
A team estimates work by multiplying the number of units by an expected number of hours per unit. Which estimating approach is it using?
- A
Applying a rate to a quantity, such as hours per unit
- B
Asking people familiar with the work to estimate its duration
- C
Using a comparable past activity and adjusting for differences
- D
Using optimistic, most likely, and pessimistic estimates
Which items does a project schedule show? Select all that apply.
- A
Activities
- B
Dependencies
- C
A guaranteed final completion date that cannot change
- D
Milestones
- E
Planned dates
When estimating an activity's duration, which factors should the team consider? Select all that apply.
- A
The work required
- B
The desired deadline, even if the work estimate must be shortened to fit it
- C
Available people and equipment and their productivity
- D
Work calendars and relevant experience or historical data
True or false: An activity's duration is its expected working time, so it may differ from the total elapsed time between its start and finish.
- A
True
- B
False
True or false: Once identified at the start of a project, the critical path cannot change as work proceeds.
- A
True
- B
False
What is the scheduling term for an activity that must occur before another activity can start or finish?
In the product-launch example, what is the duration of the critical path in working days?
In a finish-to-start relationship, the starts after the predecessor finishes.
After approval, the schedule is saved as the against which progress and changes are assessed.
A project forecast shows that a milestone will be late. Describe a sound response that addresses both how the team should evaluate options and how it should handle a change to the approved plan.
An activity can be delayed by one day without affecting its successor's start or the project finish. Which scheduling concept describes that flexibility?
- A
The time an activity must wait before its predecessor begins
- B
The time an activity can slip without delaying a specified successor or project finish
- C
The total working time needed to complete an activity
- D
The gap between the baseline date and the actual finish date
A team schedules approval of a launch plan as a milestone. In a project schedule, this milestone would usually have zero duration. True or false?
- A
True
- B
False
A project manager wants to show planned activities as bars across a timeline. Which schedule view is designed for this purpose?
- A
A network diagram
- B
A Gantt chart
- C
A milestone register
- D
A resource calendar
A team estimates assembly time by applying a known number of labor hours per unit to the number of units required. Which estimating approach is it using?
- A
Expert judgment
- B
Analogous estimating
- C
Parametric estimating
- D
Three-point estimating
After a proposed schedule has been reviewed and approved, what is the main purpose of saving it as the baseline?
- A
Use the approved schedule as the reference plan for assessing progress and changes.
- B
Replace the approved schedule with each new forecast, without retaining the earlier plan.
- C
Use the schedule only to record actual finish dates.
- D
Treat the baseline as a list of activities without planned dates.
An activity can slip by two working days without delaying its specified successor or the project finish. What is this scheduling flexibility called?
An activity has an optimistic duration of 2 working days, a most likely duration of 4 working days, and a pessimistic duration of 6 working days. Using the common weighted three-point estimate, what is its estimated duration?
All dependencies are finish-to-start. Activity A takes 2 working days. B takes 3 days after A, and C takes 4 days after A. D takes 5 days after both B and C, and E takes 2 days after D. Which route is the critical path, and what is the earliest planned project finish?
- A
A–B–D–E; 12 working days
- B
A–C–D–E; 13 working days
- C
A–B–D–E; 13 working days
- D
A–C–D–E; 11 working days