Free Online Flashcard Deck

4 Project Resources and Budgeting Free Online FlashCards

Study 4 Project Resources and Budgeting with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What counts as a project resource?

Back

People, equipment, materials, facilities, services, and funds needed to complete project work.

02
Front

What should resource planning establish for each activity?

Back

For each activity, identify the needed resource, quantity, timing and duration, responsible provider or approver, and availability.

03
Front

What does a responsibility matrix clarify?

Back

It clarifies who performs, approves, advises on, or receives information about each work item.

04
Front

What information does a resource calendar record?

Back

It records when resources are available, such as staff assignments, equipment reservations, holidays, and supplier lead times.

05
Front

What can a team do when resource demand exceeds capacity?

Back

Adjust task timing or sequence, reassign work, train staff, acquire equipment, or contract for services.

06
Front

What is a project cost estimate?

Back

A reasoned forecast of what the planned work is likely to cost, based on defined scope, schedule, assumptions, and supporting data.

07
Front

How does analogous estimating work?

Back

Use the cost of a similar completed project, adjusted for differences.

08
Front

How does parametric estimating work?

Back

Apply a cost rate to a measurable quantity, such as cost per installed unit.

09
Front

What is bottom-up estimating?

Back

Estimate individual activities or work packages and add them together; its detail depends on the quality of the underlying plan.

10
Front

How does three-point estimating represent cost uncertainty?

Back

It considers optimistic, most likely, and pessimistic costs. A commonly used weighted estimate is O+4M+P6\frac{O + 4M + P}{6}.

11
Front

How do direct and indirect project costs differ?

Back

Direct costs relate to project work, such as labor or materials; indirect costs, such as overhead, are applied using consistent rates.

12
Front

How does a project budget differ from a cost estimate?

Back

An estimate forecasts likely costs; a budget allocates funding to planned work over time.