5 Quantitative Risk Analysis Free Online FlashCards

Study 5 Quantitative Risk Analysis with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What does quantitative risk analysis assess?

Back

Quantitative risk analysis uses numerical estimates to assess how uncertainty may affect project cost, schedule, and performance, helping teams compare alternatives and focus responses.

02
Front

How is expected monetary value calculated?

Back

Expected monetary value is the sum of each outcome’s probability multiplied by its monetary value: EMV=∑i=1npixi\text{EMV} = \sum_{i=1}^{n} p_i x_i.

03
Front

What does an EMV represent—and what does it not predict?

Back

EMV is a probability-weighted average across possible outcomes, not a prediction of what will happen in a particular case.

04
Front

How should threats and opportunities be represented in EMV?

Back

Record threat impacts as losses and opportunity impacts as gains when calculating EMV.

05
Front

What should exhaustive outcome probabilities sum to?

Back

If the outcomes are exhaustive, their probabilities should sum to 11.

06
Front

When is it appropriate to add several risk EMVs?

Back

Add EMVs only when estimates share a consistent scope and time frame. Dependencies between risks can make a simple sum misleading.

07
Front

What do the three main parts of a decision tree represent?

Back

A decision node marks a choice, a chance node marks uncertain outcomes and their probabilities, and terminal branches show resulting payoffs or costs.

08
Front

How do you evaluate a decision tree?

Back

Calculate EMV at each chance node, then work backward toward the decision node and choose the alternative with the best expected result.

09
Front

Which supplier has the lower expected cost in the example?

Back

The more reliable supplier has the lower expected cost: $112,000+(0.05×$50,000)=$114,500\$112{,}000 + (0.05 \times \$50{,}000) = \$114{,}500, which is $500\$500 below the standard supplier’s $115,000\$115{,}000.

10
Front

How does sensitivity analysis test a project estimate?

Back

Sensitivity analysis varies one input at a time while holding other assumptions constant, then compares how the estimate or decision changes.

11
Front

What does a tornado chart show in sensitivity analysis?

Back

A tornado chart ranks factors according to how much each one changes the result.

12
Front

What is the standard supplier’s expected cost if delay probability rises to 40%40\%?

Back

At a delay probability of 40%40\%, the standard supplier’s expected cost is $100,000+(0.40×$50,000)=$120,000\$100{,}000 + (0.40 \times \$50{,}000) = \$120{,}000.