6 Planning Responses to Project Risks Free Online FlashCards

Study 6 Planning Responses to Project Risks with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What should guide the choice of a project risk response?

Back

Consider likelihood, potential effect, timing, urgency, and the response’s cost and side effects. Choose an approach proportionate to the risk and feasible within the project’s authority, schedule, and budget.

02
Front

What does avoiding a project threat mean?

Back

Avoidance changes the approach, scope, or plan so the threat can no longer affect the project.

03
Front

What does exploiting an opportunity mean?

Back

Exploitation means acting to make the opportunity happen.

04
Front

When is escalation a suitable risk response?

Back

Escalation raises the risk to the appropriate organizational level for a decision when it is outside the project’s authority or scope.

05
Front

How do a risk owner and an action owner differ?

Back

The risk owner is accountable for monitoring the risk and coordinating its response. An action owner may separately be assigned to carry out a specific task.

06
Front

How do a response trigger and contingency differ?

Back

A trigger is a measurable sign or event that calls for a planned action. A contingency is the fallback action if a threat occurs, or the action to capture an opportunity when its trigger appears.

07
Front

What are residual and secondary risks?

Back

Residual risk is exposure remaining after the planned response. Secondary risks are new risks the response itself may create; both should be recorded and assessed.

08
Front

How should approved response work be integrated into a project?

Back

Add approved response actions to work packages, schedules, and team assignments, and estimate their resources and costs. Include them in the appropriate plans or baselines under approval and change-control rules.

09
Front

What is threat mitigation?

Back

Mitigation reduces the likelihood of the threat, its impact, or both.

10
Front

What does transferring or sharing a threat do?

Back

It arranges for another party to carry or share part of the exposure, for example through insurance or a contract. The project may retain some risk.

11
Front

What does accepting a threat involve?

Back

Threat acceptance is a deliberate choice to take no proactive action beyond monitoring, or to prepare a contingency response if the threat occurs.

12
Front

What is opportunity enhancement?

Back

Enhancement increases the likelihood of the opportunity or the benefit it would provide.