7 Monitoring, Controlling, and Communicating Project Risks Free Online FlashCards

Study 7 Monitoring, Controlling, and Communicating Project Risks with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What is a risk indicator?

Back

An observable measure or warning sign that shows whether a risk is changing in likelihood or consequence, or nearing occurrence.

02
Front

What is a risk trigger?

Back

A threshold or event that signals a planned response should begin or that the risk has become an issue.

03
Front

What key information should a risk register contain for each significant risk?

Back

Record the risk description and potential effect, owner, indicators or triggers and their checks, and the response, action owner, due date, and status.

04
Front

What should regular project risk reviews examine?

Back

Check whether existing risks have changed, new risks have emerged, and planned actions are working. Review relevant evidence such as schedule, cost, quality, dependencies, suppliers, and assumptions.

05
Front

How should teams reassess a project's risk exposure?

Back

Reassess likelihood and impact using agreed project scales, considering effects on scope, time, cost, quality, safety, and expected benefits.

06
Front

What should happen when an uncertain risk event occurs?

Back

Manage it as an issue with an owner and action plan, and record any remaining risks the issue creates.

07
Front

How should teams put an agreed risk response into action?

Back

Integrate actions into the schedule, budget, and assigned work; confirm owners, deadlines, dependencies, and approval requirements.

08
Front

What should a useful risk report or dashboard communicate?

Back

Tailor timely updates to stakeholder responsibilities. Summarize significant exposures, changes, indicators and triggers, response progress, residual exposure, and decisions or support needed.

09
Front

What should teams capture when recording lessons from a risk response?

Back

Capture what happened, its cause, which indicators warned of it, whether the response worked, and what should change in future practice. Apply useful lessons to the current project too.

10
Front

What makes a risk indicator useful in a dashboard?

Back

Choose relevant, observable indicators. A useful dashboard shows their trends and whether they crossed agreed thresholds, not just a risk rating without context.

11
Front

How should teams set the frequency of risk reviews?

Back

Set review frequency in proportion to risk level, pace of change, and project context; review urgent or rapidly changing exposures more often.

12
Front

What is a secondary risk, and how might a backup supplier create one?

Back

A response can create secondary risks. For example, a backup supplier may reduce delay exposure but introduce extra cost or integration risk.