Study 6 Business Environment and Value Delivery with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What is a project’s business context?

Back

A project’s business context is its internal and external setting. It includes factors such as strategy, governance, resources, market conditions, technology, and regulations.

02
Front

What does a business case explain?

Back

It explains why the project is worth undertaking by connecting organizational needs with expected outcomes, benefits, costs, risks, and strategic objectives. Revisit it when assumptions or circumstances change.

03
Front

What chain connects strategy to project value?

Back

Strategic objective → business need → project output → operational outcome → benefit → value.

04
Front

How does an output differ from an outcome?

Back

An output is what the project delivers; an outcome is the result of using that output. For example, a support portal is an output, while customers resolving issues without repeat contact is an outcome.

05
Front

How should an organization judge project value?

Back

Value considers benefits alongside the effort, expense, risks, and stakeholder effects involved. Meeting delivery targets alone does not prove that a project created worthwhile value.

06
Front

What does project compliance mean?

Back

Compliance is conformance with applicable obligations and requirements, such as laws, contracts, policies, security, privacy, health and safety, quality, or sustainability requirements.

07
Front

How should a project manage compliance?

Back

Identify and classify requirements, determine their effects, assess threats, build controls into plans and work, and monitor evidence. Escalate gaps through defined governance channels.

08
Front

What does project change control govern?

Back

Project change control evaluates proposed changes to requirements, scope, baselines, plans, or deliverables, obtains required decisions, and implements approved changes. An unapproved request does not authorize a baseline change.

09
Front

What is organizational change management?

Back

Organizational change management prepares and supports people and operations moving from the current state to a future state. It addresses readiness, impacts, communication, training, adoption, and sustaining new practices.

10
Front

What is a project benefit?

Back

A benefit is a measurable improvement or advantage resulting from an outcome. It may be financial, operational, customer-related, risk-reducing, or intangible.

11
Front

What should a benefits approach define?

Back

A benefits approach identifies the intended benefit, baseline and target where feasible, measurement method and timing, accountable benefit owner, dependencies, assumptions, and required organizational changes.

12
Front

Why track benefits after project closure?

Back

Benefits often emerge after handover, so measurement and oversight should continue after project closure. Ownership should transition to the people responsible for operations.