5 Predictive, Agile, and Hybrid Delivery Online Quiz Questions

Use this free practice quiz with 20 questions to review 5 Predictive, Agile, and Hybrid Delivery, test your knowledge, and prepare for your next test or exam.

20 questions
01
True or false
1 point

True or false: Every project life cycle includes planning, although the timing and detail of planning vary by delivery approach.

  1. A

    True

  2. B

    False

02
Choose one
1 point

A project has stable requirements, several dependent work packages, and contractual terms that make changes costly. Which delivery approach is the best initial fit?

  1. A

    Use an adaptive approach because it is always preferable when a project has dependencies.

  2. B

    Use a predictive approach because the requirements are stable and changes are costly.

  3. C

    Use an adaptive approach because predictive work does not include feedback.

  4. D

    Use a hybrid approach because all projects must combine predictive and adaptive practices.

03
Fill in the blank
1 point

A team repeatedly tests and revises a dashboard layout to improve it; this is development. A service that adds account creation first and payments later is an example of development.

04
Written response
1 point

An adaptive team plans its next work in detail but keeps later work at a higher level until it learns more. What is this planning practice called?

05
Choose one
1 point

A team expects users to clarify their needs as they try early versions of a product. Which approach best supports learning and adjustment through frequent cycles?

  1. A

    Predictive, because all work must be fully specified before development starts.

  2. B

    Predictive, because frequent user feedback is incompatible with controlled delivery.

  3. C

    Adaptive, because the team can learn from users and adjust the solution in short cycles.

  4. D

    Hybrid, because any project with uncertain features must use formal predictive phases.

06
True or false
1 point

True or false: In a predictive project, a proposed change cannot be made once the initial plan has been approved.

  1. A

    True

  2. B

    False

07
Choose all
1 point

Which practices are consistent with adaptive delivery? Select all correct choices.

  1. A

    Maintain an ordered backlog to guide attention toward valuable or urgent work.

  2. B

    Avoid planning until the entire solution is known.

  3. C

    Plan near-term work in detail while keeping later work at a higher level.

  4. D

    Deliver and review small increments frequently, then use feedback to adjust.

08
Written response
1 point

In Scrum, which event focuses on improving how the team works?

09
Fill in the blank
1 point

In Scrum, a Sprint aims to produce a usable that meets the .

10
Choose all
1 point

A project team is tailoring its delivery approach. Which considerations should inform that choice? Select all correct choices.

  1. A

    How uncertain the requirements and solution are.

  2. B

    The impact of failure and the verification or traceability needed.

  3. C

    Whether a delivery method is currently fashionable.

  4. D

    Fixed dates, regulatory obligations, procurement commitments, or dependencies.

  5. E

    Whether stakeholders can provide timely feedback.

  6. F

    Whether the project can remove required legal and safety controls.

11
Choose one
1 point

A Scrum team wants to inspect its latest outcome with stakeholders and discuss what adaptations may be useful next. Which Scrum event best fits this purpose?

  1. A

    Sprint Retrospective

  2. B

    Sprint Review

  3. C

    Sprint Planning

  4. D

    Daily Scrum

12
Choose one
1 point

A customer portal has a fixed launch date and formal security approvals, but its self-service features are still uncertain. Which plan best fits these conditions?

  1. A

    Use only predictive delivery because a fixed launch date means features cannot change.

  2. B

    Use only adaptive delivery and remove formal approvals to preserve iteration speed.

  3. C

    Use predictive planning for budget, milestones, security controls, and release gates, while developing uncertain features iteratively with user feedback.

  4. D

    Choose a single method for every component because hybrid delivery is a prescribed method.

13
Choose one
1 point

A regulated project team wants to tailor its practices to support iterative development. What should it do about required safety and governance controls?

  1. A

    Remove safety reviews if iterative development is being used.

  2. B

    Adjust delivery practices to fit the project while retaining required safety and governance controls.

  3. C

    Replace all organizational approval requirements with user feedback.

  4. D

    Keep every practice unchanged because tailoring is not permitted in regulated work.

14
Open ended
1 point

A team is developing a safety-critical product. Its safety verification and approval requirements are fixed, but the user interface is not yet well understood. Recommend a delivery approach and explain how the team should handle each part.

15
Choose one
1 point

A project has stable requirements, and a contract makes changes expensive. Which delivery approach best fits this situation?

  1. A

    Use adaptive delivery because it avoids formal change controls.

  2. B

    Use predictive delivery, planning substantial scope early and managing changes through agreed controls.

  3. C

    Use hybrid delivery because every project must combine predictive and adaptive practices.

  4. D

    Use incremental delivery because it requires all requirements to be fixed at the outset.

16
Choose one
1 point

A team is building a product whose requirements are still emerging. Which planning pattern best supports learning while coordinating work?

  1. A

    Detail near-term work, keep future work at a higher level, and revise plans as the team learns.

  2. B

    Complete a fully detailed plan for the entire project before beginning delivery.

  3. C

    Avoid planning until users have reviewed the completed solution.

  4. D

    Fix the backlog permanently at the start so feedback cannot change priorities.

17
True or false
1 point

True or false: An adaptive approach means the team does not plan its work.

  1. A

    True

  2. B

    False

18
Written response
1 point

A team tests a basic dashboard with users, then revises its layout and functions in later cycles. What development concept describes improving a solution through repetition?

19
Written response
1 point

What planning term describes detailing near-term work while keeping future work at a higher level until more is known?

20
Choose one
1 point

A team plans to make an online service usable first for account creation, then for payments, and later for reporting. Which development concept best describes this pattern?

  1. A

    Predictive development, because all phases must be completed in sequence.

  2. B

    Iterative development, because it means adding separate usable capabilities over time.

  3. C

    Incremental development, because it adds usable pieces of the solution over time.

  4. D

    Tailoring, because it means adding features to a product.