2 Scope Planning and Control Free Online FlashCards

Study 2 Scope Planning and Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.

12 cards
01
Front

What does project scope define?

Back

Project scope defines the work and deliverables required to meet project objectives, as well as the work that is excluded.

02
Front

What should a project scope statement identify?

Back

It identifies objectives and deliverables, in-scope and out-of-scope work, acceptance criteria, assumptions, and constraints.

03
Front

What makes a project requirement useful?

Back

A requirement should be clear and testable so the team can verify whether it has been met.

04
Front

Name three ways to gather stakeholder requirements.

Back

Methods include interviews, workshops, observation, document review, and surveys.

05
Front

What does a requirements traceability matrix connect?

Back

It links each requirement to its source, related deliverable, and verification or acceptance method.

06
Front

What is a work breakdown structure (WBS)?

Back

A WBS is a hierarchical decomposition of the project’s total scope into manageable components.

07
Front

What typically makes up the scope baseline?

Back

It typically includes the approved scope statement, WBS, and WBS dictionary.

08
Front

How should a team handle a request for extra work?

Back

Record the request, assess its impacts, and seek an authorized decision before starting the extra work. If approved, update affected plans and baselines; this helps prevent scope creep.

09
Front

What are acceptance criteria?

Back

Acceptance criteria are the conditions a deliverable must meet to be accepted.

10
Front

How should a WBS be organized?

Back

Organize it around deliverables—the project’s outputs—not merely activities or a timeline.

11
Front

What is a work package?

Back

A work package is a decomposed WBS component whose work can be estimated, assigned, and controlled.

12
Front

What does the WBS 100% rule require?

Back

The WBS must include all work required by the approved scope and no work outside it; child elements at each level represent the full work of their parent.