Learn how to build a logic-linked project schedule, estimate durations, calculate critical paths and float, protect the approved baseline, and respond to forecast delays.

How a project schedule works

A project schedule is a logic-linked model of the work. It shows what must happen, in what order, for how long, and when the project is forecast to finish. Reliable schedule practice combines realistic activity sequencing and duration estimates with critical-path analysis, an approved baseline, and disciplined updates. A reliable schedule is comprehensive, well-constructed, credible, and controlled.

Sequence activities and dependencies

Break the project scope into work activities and milestones, then link each activity to its logical predecessors. In a relationship, a successor cannot start until its predecessor finishes. Other relationships, such as start-to-start, may be useful when work genuinely overlaps.

Avoid artificial links, unjustified lags, and fixed-date constraints that conceal the actual work sequence. The schedule should show genuine dependencies rather than force all work into one sequence.

For example, requirements must precede both design and equipment ordering. Design precedes software build, while ordering precedes equipment receipt. Integration waits for both software build and equipment receipt, and acceptance follows integration. This allows design and ordering to proceed in parallel after requirements are defined.

Estimate activity durations

Estimate each activity's duration from its scope, expected resources, working calendar, and relevant past performance. Record important assumptions: a duration is not meaningful without specifying the work and conditions it includes.

When uncertainty is material, a can express optimistic duration OO, most likely duration MM, and pessimistic duration PP. A common PERT expected-duration calculation is:

Expected duration=O+4M+P6\text{Expected duration} = \frac{O + 4M + P}{6}

For testing estimated at 22 days optimistically, 44 days most likely, and 88 days pessimistically, the calculation is:

2+4×4+86=266≈4.33 working days\frac{2 + 4 \times 4 + 8}{6} = \frac{26}{6} \approx 4.33\text{ working days}

This result is an estimate, not a promise or guaranteed finish date. Select a practical schedule duration and document the assumptions and any separate contingency.

Calculate the and float

The is the longest-duration path through the network. Given the schedule's logic and assumptions, it determines the earliest possible project finish. Activities on that path typically have zero . is the amount of time an activity can slip without delaying the forecast project finish.

For a simple network in which all links are finish-to-start, use a to find earliest dates:

  • Earliest finish is earliest start plus duration: EF=ES+dEF = ES + d.

  • A successor's earliest start is the latest earliest finish among its predecessors.

Use a to find the latest dates that will not delay the finish:

  • Latest start is latest finish minus duration: LS=LF−dLS = LF - d.

  • A predecessor's latest finish is the earliest latest start among its successors.

  • is LS−ESLS - ES, equivalently LF−EFLF - EF.

Worked network

Start at day 00; durations are working days, and every link is finish-to-start. The activities and dependencies are:

  • Activity A, define requirements: 22 days, no predecessor.

  • Activity B, design solution: 44 days, after A.

  • Activity C, procure equipment: 55 days, after A.

  • Activity D, build software: 33 days, after B.

  • Activity E, receive equipment: 11 day, after C.

  • Activity F, integrate and test: 22 days, after D and E.

  • Activity G, acceptance: 11 day, after F.

The two main paths are A–B–D–F–G, with duration 2+4+3+2+1=122 + 4 + 3 + 2 + 1 = 12 working days, and A–C–E–F–G, with duration 2+5+1+2+1=112 + 5 + 1 + 2 + 1 = 11 working days. The earliest project finish is 1212 working days, and A–B–D–F–G is the . The procurement path has 11 day of .

The forward- and backward-pass results are:

  • A: ES=0ES = 0, EF=2EF = 2, LS=0LS = 0, LF=2LF = 2, 00.

  • B: ES=2ES = 2, EF=6EF = 6, LS=2LS = 2, LF=6LF = 6, 00.

  • C: ES=2ES = 2, EF=7EF = 7, LS=3LS = 3, LF=8LF = 8, 11.

  • D: ES=6ES = 6, EF=9EF = 9, LS=6LS = 6, LF=9LF = 9, 00.

  • E: ES=7ES = 7, EF=8EF = 8, LS=8LS = 8, LF=9LF = 9, 11.

  • F: ES=9ES = 9, EF=11EF = 11, LS=9LS = 9, LF=11LF = 11, 00.

  • G: ES=11ES = 11, EF=12EF = 12, LS=11LS = 11, LF=12LF = 12, 00.

If equipment receipt (E) slips by 22 working days and nothing else changes, its 11 day of float is used and the project is delayed by 11 working day. The procurement path becomes critical. Recalculate the network after changes instead of assuming the original remains the only path that matters.

Maintain the

A is the approved target schedule used to plan and measure performance. It should reflect authorized scope, activity logic, durations, calendars, key assumptions, and milestones.

Keep the baseline distinct from the current forecast. Update the forecast using actual progress and estimates of remaining duration, then compare forecast dates with baseline dates to identify variances. Document reasons for changes and manage proposed baseline changes through the project's approval or change-control process; do not silently overwrite the target plan.

For example, if integration has a baseline start on day 99, but an update forecasts a day 1010 start because equipment will arrive late, retain the day 99 baseline, enter the day 1010 forecast, and report the one-day variance. Explain its cause and effect on downstream work and the finish forecast. If an approved scope or plan change warrants a new baseline, retain appropriate change records rather than treating the revised target as if it had always been the plan.

Recover from schedule delays

Schedule recovery aims to reduce a forecast delay while preserving required scope and quality. Assess cost, feasibility, risk, and effects on all paths before changing the plan.

  • adds resources, overtime, or other cost to shorten an activity. Target work on the current : shortening a noncritical activity may not improve the finish date.

  • performs activities in parallel that were originally planned in sequence. It can introduce coordination, rework, or quality risks.

  • Re-sequencing or removing constraints changes the plan only when the work and dependencies genuinely permit it.

After a recovery change, recalculate the network and check whether another path becomes critical. Schedule updates should use actual progress and valid logic, and recovery actions and their effects should be visible in the forecast.

In the example network, software build (D) is forecast to take 55 days instead of its 33-day baseline duration, adding 22 days to the . Paying for extra resources to return D's forecast duration to 33 days may restore the original 1212-day finish if both days are recovered and no other work has slipped. Confirm that the work can be staffed and performed safely without reducing required quality, record the added cost and assumptions, update the forecast, and verify the other path and downstream dates. Do not change baseline dates unless the authorized change-control process approves a baseline change.