What does a finish-to-start relationship require?
A finish-to-start relationship means the successor cannot start until the predecessor finishes.
Study 3 Schedule Planning and Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.
What does a finish-to-start relationship require?
A finish-to-start relationship means the successor cannot start until the predecessor finishes.
Which activities can proceed in parallel after requirements?
After requirements are defined, design and equipment ordering can proceed in parallel because both depend on requirements, not on each other.
What should inform an activity duration estimate?
Estimate duration from the activity’s scope, expected resources, working calendar, and relevant past performance. Record assumptions so the estimate’s conditions are clear.
What determines the critical path?
The critical path is the longest-duration path through the network; it determines the earliest possible project finish under the schedule’s logic and assumptions.
What does total float measure?
Total float is how long an activity can slip without delaying the forecast project finish.
How is earliest finish calculated in a forward pass?
For a forward pass, earliest finish is earliest start plus duration: EF=ES+duration.
How do predecessors determine a successor’s earliest start?
A successor’s earliest start is the latest earliest finish among its predecessors.
How does a backward pass calculate latest start?
In a backward pass, latest start is latest finish minus duration: LS=LF−duration. A predecessor’s latest finish is the earliest latest start among its successors.
Which path is critical in the example network?
In the example network, A–B–D–F–G is critical, with a total duration of 12 working days.
How much total float does the example’s procurement path have?
The procurement path A–C–E–F–G has 1 working day of total float in the example network.
What happens if equipment receipt slips by 2 working days?
A 2-working-day slip in equipment receipt uses its 1 day of float and delays the project finish by 1 working day. The procurement path becomes critical.
What is a schedule baseline?
The approved target schedule used to plan and measure performance is the schedule baseline. It reflects authorized scope, logic, durations, calendars, assumptions, and milestones.
A medium-difficulty quiz on the RBT role, behavior-analytic concepts, supervision, and professional practice.
Learn the RBT’s supervised role, core behavior-analytic concepts, and professional responsibilities for delivering services safely and ethically.
A medium-difficulty quiz on defining behavior, selecting and applying measurement procedures, and interpreting behavior data.
Learn how to define observable behavior, select and apply measurement procedures, calculate basic outcomes, and interpret data with appropriate context.
A medium-difficulty quiz on applying behavior-reduction procedures, distinguishing reinforcement and punishment concepts, and following an RBT’s implementation and safety responsibilities.
Review accurate session notes, truthful records, timely reporting, incident response, and client-information privacy for RBT practice.
A medium-difficulty quiz on objective documentation, accurate records, reporting responsibilities, and client privacy in RBT practice.
Learn how RBTs document sessions and services accurately, report changes and incidents promptly, and protect client information.
A medium-difficulty quiz on applying ethical standards and professional practices in Registered Behavior Technician work.
Learn how Registered Behavior Technicians protect client rights and well-being, maintain professional standards, and respond to ethical concerns through supervision and required procedures.
An application-focused review of integrated RBT practice, including measurement, assessment, teaching, safety, documentation, and professional ethics.
Connects measurement, assessment, teaching, behavior reduction, documentation, and ethics to the RBT’s responsibilities in integrated practice.