What does a cost estimate forecast?
A cost estimate forecasts the resources needed to complete specified work.
Study 4 Cost Planning and Control with 12 free online flashcards. Review key terms, definitions, and concepts with this interactive flashcard deck.
What does a cost estimate forecast?
A cost estimate forecasts the resources needed to complete specified work.
How does analogous estimating work?
Use actual costs from a similar project and adjust them for differences. This approach is useful early, when project detail is limited.
What is parametric cost estimating?
Apply a cost rate to a measurable quantity, such as a cost per unit. The rate and quantity must fit the work being estimated.
How does bottom-up estimating build a project estimate?
Estimate detailed activities or work packages, then aggregate their costs. It can be detailed but requires a sufficiently defined scope.
What weighted formula is commonly used for three-point estimating?
It combines optimistic, most likely, and pessimistic estimates using 6O+4M+P, where O, M, and P are those estimates.
What makes a cost contingency a defensible planning allowance?
It is an explicit planning allowance for identified uncertainty, supported by risk analysis—not an unexplained cushion.
How does a budget differ from a cost estimate?
An estimate forecasts expected cost; a budget is authorized funding for the project or part of it.
What is a cost baseline?
It is the approved, time-phased budget used to measure and control cost performance. In common earned value practice, it includes authorized work and contingency reserve, but excludes management reserve.
How do Planned Value and Earned Value differ?
Planned Value (PV) is the budgeted value of work scheduled by the status date; Earned Value (EV) is the budgeted value of work actually completed.
What does Actual Cost measure in earned value management?
Actual Cost (AC) is the cost incurred for the work completed.
How is Cost Variance calculated, and what does a negative result mean?
Cost Variance is CV=EV−AC. A negative result is unfavorable: completed work cost more than its budgeted value.
How is CPI calculated, and what does a value below 1.0 signal?
Cost Performance Index is CPI=ACEV. Below 1.0 indicates unfavorable cost efficiency; above 1.0 indicates favorable efficiency.
A medium-difficulty quiz on the RBT role, behavior-analytic concepts, supervision, and professional practice.
Learn the RBT’s supervised role, core behavior-analytic concepts, and professional responsibilities for delivering services safely and ethically.
A medium-difficulty quiz on defining behavior, selecting and applying measurement procedures, and interpreting behavior data.
Learn how to define observable behavior, select and apply measurement procedures, calculate basic outcomes, and interpret data with appropriate context.
Learn how RBTs prepare for and implement written skill-acquisition plans, including teaching formats, prompting, reinforcement, measurement, generalization, and maintenance.
Review the functions of behavior, common behavior-reduction procedures, and the RBT’s responsibilities for safe and authorized implementation.
A medium-difficulty quiz on applying behavior-reduction procedures, distinguishing reinforcement and punishment concepts, and following an RBT’s implementation and safety responsibilities.
Review accurate session notes, truthful records, timely reporting, incident response, and client-information privacy for RBT practice.
A medium-difficulty quiz on objective documentation, accurate records, reporting responsibilities, and client privacy in RBT practice.
Learn how RBTs document sessions and services accurately, report changes and incidents promptly, and protect client information.
Review ethical RBT practice, including client dignity and privacy, professional boundaries, cultural responsiveness, and the importance of working within competence and seeking supervision.
An application-focused review of integrated RBT practice, including measurement, assessment, teaching, safety, documentation, and professional ethics.