True or false: In a finish-to-start relationship, the successor activity may start before the predecessor activity finishes.
3 Schedule Planning and Control Online Quiz Questions
Use this free practice quiz with 20 questions to review 3 Schedule Planning and Control, test your knowledge, and prepare for your next test or exam.
A project requires requirements to be defined before both design and equipment ordering. There is no dependency between design and ordering. Which schedule logic best represents these dependencies?
- A
Design must finish before ordering can begin.
- B
Design and ordering can begin in parallel after requirements are defined.
- C
Ordering must finish before design can begin.
- D
Design and ordering must both finish before requirements can be defined.
The approved target schedule used to plan and measure performance is the .
A finish-to-start activity has two predecessors with earliest finishes on days 8 and 10. What is the successor’s earliest start?
- A
Day 8, the earlier predecessor finish
- B
Day 10, the later predecessor finish
- C
Day 18, the sum of both predecessor finishes
- D
Day 2, the difference between the predecessor finishes
An activity has an optimistic duration of 2 working days, a most likely duration of 4 working days, and a pessimistic duration of 8 working days. Using E=6O+4M+P, what is its expected duration, rounded to the nearest hundredth of a working day?
Select all factors identified as relevant when estimating an activity's duration.
- A
The activity's scope.
- B
Expected resources.
- C
The working calendar.
- D
A fixed finish date chosen without estimating the work.
- E
Relevant past performance.
Adding resources or overtime, often at additional cost, to shorten an activity is called .
What schedule recovery technique overlaps activities that were originally planned in sequence?
In a schedule, equipment receipt has 1 working day of total float. If it slips by 2 working days and no other work changes, what is the likely effect?
- A
The finish remains unchanged because equipment receipt has float.
- B
The finish is delayed by 1 working day, and the procurement path becomes critical.
- C
The finish is delayed by 2 working days, and the original critical path remains the only critical path.
- D
The finish is delayed by 1 working day, but the procurement path still has 1 day of float.
The approved schedule baseline calls for integration to start on day 9. The updated forecast is a day-10 start because equipment will arrive late. What should the project manager report and how should the baseline be handled?
After making a schedule recovery change, which actions are appropriate? Select all that apply.
- A
Update the forecast using actual progress and valid logic.
- B
Recalculate the network and check whether another path becomes critical.
- C
Check the recovery action's feasibility and effect on cost and quality.
- D
Assume the original critical path remains the only critical path without recalculating.
- E
Record the recovery action and its assumptions.
True or false: After a schedule change, the project team can assume the original critical path is still the only critical path without recalculating the network.
- A
True
- B
False
A team shortens an activity that is not on the current critical path, while leaving all other work and logic unchanged. What is the most likely effect on the forecast project finish?
- A
The forecast finish must move earlier by the full amount of time saved.
- B
The forecast finish may not change because shortening noncritical work may not affect the project finish.
- C
The project must extend its baseline by the amount saved.
- D
The activity becomes critical automatically.
True or false: A project team should remove a schedule constraint or change activity order only when the work and its genuine dependencies permit that change.
- A
True
- B
False
A project manager links two activities with a finish-to-start relationship. What does this relationship require?
- A
The successor may start before the predecessor starts.
- B
The successor cannot start until the predecessor finishes.
- C
The predecessor cannot start until the successor finishes.
- D
The activities must start and finish at the same time.
A project requires requirements to be defined before both design and equipment ordering. Design must precede software build, but no dependency is specified between design and ordering. Which schedule logic is appropriate?
- A
Design must finish before equipment ordering can begin.
- B
Equipment ordering must finish before design can begin.
- C
Design and equipment ordering can proceed in parallel after requirements.
- D
Software build can begin before design is complete.
What schedule term describes how long an activity can slip without delaying the forecast project finish?
An activity has an optimistic duration of 2 working days, a most likely duration of 4 working days, and a pessimistic duration of 8 working days. Using the PERT expected-duration calculation 6O+4M+P, what is the expected duration? Round to two decimal places.
A project network has two main paths: A–B–D–F–G takes 12 working days, and A–C–E–F–G takes 11 working days. Which path is critical?
- A
A–B–D–F–G, because it takes 12 days.
- B
A–C–E–F–G, because it contains equipment procurement.
- C
Both paths, because they share activities.
- D
Neither path, because their durations differ.
Two activities have finish-to-start links to a successor. Their earliest finish days are 5 and 7. On what day does the successor earliest start?
- A
Day 5, because the successor starts after the first predecessor.
- B
Day 6, the average of the predecessor finish days.
- C
Day 7, the later of the two predecessor finish days.
- D
Day 12, the sum of both predecessor finish days.
Related study packs and tools
- Quiz
1 RBT Foundations and Professional Role
A medium-difficulty quiz on the RBT role, behavior-analytic concepts, supervision, and professional practice.
RBT Practice TestUpdated - Study guide
1 RBT Foundations and Professional Role
Learn the RBT’s supervised role, core behavior-analytic concepts, and professional responsibilities for delivering services safely and ethically.
RBT Practice TestUpdated - Quiz
2 Measurement and Data Collection
A medium-difficulty quiz on defining behavior, selecting and applying measurement procedures, and interpreting behavior data.
RBT Practice TestUpdated - Study guide
2 Measurement and Data Collection
Learn how to define observable behavior, select and apply measurement procedures, calculate basic outcomes, and interpret data with appropriate context.
RBT Practice TestUpdated - Study guide
4 Skill Acquisition Procedures
Learn how RBTs prepare for and implement written skill-acquisition plans, including teaching formats, prompting, reinforcement, measurement, generalization, and maintenance.
RBT Practice TestUpdated - Flashcards
5 Behavior-Reduction Procedures
Review the functions of behavior, common behavior-reduction procedures, and the RBT’s responsibilities for safe and authorized implementation.
RBT Practice TestUpdated - Quiz
5 Behavior-Reduction Procedures
A medium-difficulty quiz on applying behavior-reduction procedures, distinguishing reinforcement and punishment concepts, and following an RBT’s implementation and safety responsibilities.
RBT Practice TestUpdated - Flashcards
6 Documentation and Reporting
Review accurate session notes, truthful records, timely reporting, incident response, and client-information privacy for RBT practice.
RBT Practice TestUpdated - Quiz
6 Documentation and Reporting
A medium-difficulty quiz on objective documentation, accurate records, reporting responsibilities, and client privacy in RBT practice.
RBT Practice TestUpdated - Study guide
6 Documentation and Reporting
Learn how RBTs document sessions and services accurately, report changes and incidents promptly, and protect client information.
RBT Practice TestUpdated - Flashcards
7 Ethics and Professional Practice
Review ethical RBT practice, including client dignity and privacy, professional boundaries, cultural responsiveness, and the importance of working within competence and seeking supervision.
RBT Practice TestUpdated - Quiz
8 Integrated Practice and Review
An application-focused review of integrated RBT practice, including measurement, assessment, teaching, safety, documentation, and professional ethics.
RBT Practice TestUpdated